York Outer Ring Road (YORR) Phase 1a - Decision to enter into contract with Pell Frischmann to provide services to support delivery
30/09/2026 - York Outer Ring Road (YORR) Phase 1a - Decision to enter into contract with Pell Frischmann to provide services to support delivery
Background:
As determined at Executive on 15 July 2025, CYC are now taking a
phased approach to delivering the YORR scheme, with the immediate
priority being Phase 1A which comprises the section from A19
Shipton Road, to Wigginton Road, including Clifton Moor.
Link: Decisions - Executive - 15 July 2025
Within this same Executive Decision, approval was given “for
the procurement of contractors and specialist support services to
enable timely delivery of future phases of the YORR programme and
delegate authority to the Director of City Development, in
consultation with the Director of Governance and the Director of
Finance, to procure such contractors and/or consultants and to take
such steps as are necessary to award and enter into the resulting
contracts”
A decision is now requested to enter into contract with Pell
Frischmann Ltd to act as the council’s Technical Assurance
Partner in the delivery of this project. The value of this contract
being £1,325,405.92. Procurement has been undertaken via the
ESPO framework and is a direct award.
Critically for this project, this will enable them to continue to
support us through the development of the FBC and discharging of
the planning conditions by the deadline of 12 April 2027.
Comments/Observations:
Procurement of this contract has been undertaken with the full
involvement of CYC’s Corporate Procurement and Legal
teams.
Due to the previous decision made at Executive and the value of the
contract, this Officer Decision is being made in collaboration with
and with the endorsement of Richard Webb, Chief Executive Officer,
and Debbie Mitchell, Chief Finance Officer.
Details of Decision:
Council to enter into contract with Pell Frischmann Ltd.