Issue - meetings

Economy & Place Transport Capital Programme – 2018/19 Monitor 1 Report

Meeting: 25/10/2018 - Decision Session - Executive Member for Transport - Expired (Item 40)

40 Directorate of Economy & Place Transport Capital Programme - 2018/19 Monitor 1 Report pdf icon PDF 189 KB

This report sets out progress to date on schemes in the 2018/19 Economy & Place Transport Capital Programme, and proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections.

 

Additional documents:

Decision:

Resolved:

(i)      That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved.

(ii)      That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted

Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.

 

 

Minutes:

The Executive Member considered a report which set out progress to date on schemes in the 2018/19 Economy & Place Transport Capital Programme, and proposed adjustments to scheme allocations to align with the latest cost estimates and delivery projections.

 

The Executive Member noted the proposed programme of schemes which had been developed to implement the priorities of the Local Transport Plan (LTP3) and the Council Plan.

 

It was noted that good progress had been made on the Wetherby Road roundabout upgrade, with the majority of the construction due to be completed by mid-December, and that work on the Scarborough Bridge scheme was due to start soon with the bridge closed from January. Officers confirmed that bridge/footpath closures would be advertised clearly so that users were fully aware.

 

Resolved:

(i)           That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved.

(ii)         That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted

 

Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.

 


 