Decision details

Housing Retrofit update

Decision Maker: Executive

Decision status: Decision Made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Purpose of report: This paper will update members on the delivery of retrofit works in the city and seek approval to continue this programme of activity through further grant funded works.

Executive will be asked to: Note progress to date on the delivery of retrofit works in both the private and social housing sectors and to progress with the delivery of further grant funded retrofit works.

Decision:

Resolved:

 

                   i.        Noted the progress achieved so far in the completion of energy efficiency and retrofit projects under the following grant funded programmes, Home Upgrade Grant Phase 1 (HUG1), Local Authority Delivery Phase 3 (LAD3), and the Social Housing Decarbonisation Fund Wave 1 (SHDF1);

                  ii.        Noted the commencement of new energy efficiency and retrofit projects, including the Local Energy Advice Demonstrator (LEAD) project, Retrofit One Stop York (ROSSY) project, and the Social Housing Decarbonisation Fund Wave 2 (SHDF2).

 

HUG2

 

                 iii.        Approved the Council entering into the Home Upgrade Grant Phase 2 delivery contract with Clear Climate, as the winning bidder of the recent procurement exercise;

                iv.        Delegated authority to the Director of Housing, Economy and Regeneration in consultation with the Head of Procurement and the Director of Governance (or their delegated officers), to conclude the terms of the HUG2 contract with Clear Climate.

 

LEAD

 

                  v.        Noted the signing of a grant funding agreements, as part of the Local Energy Advice Demonstrator (LEAD), with Joseph Rowntree Housing Trust. Note the intention to enter further grant funding agreements with York Conservation Trust, York Travellers Trust, and Leeds Beckett University, to enable the delivery of high-quality retrofit surveys and advice which target properties which are ‘hard to treat’ and residents who are often missed or not engaged with. Such agreements, and the associated transfer of grant funds, will enable a significant number of retrofit surveys and thereby support effective planning for future retrofit delivery works.

 

 

 

Net Zero Fund

 

                vi.        Approved the Council entering into the Grant Funding Agreement with York and North Yorkshire Combined Authority for the Net Zero Fund allocation for Alex Lyon House and Honeysuckle House, totalling £1,895k and delegate to the Director of Housing, Economy and Regeneration, in consultation with the Head of Procurement and Director of Governance (or their delegated officers), authority to conclude terms of the grant funding agreement;

               vii.        Delegated authority to the Director of Housing, Economy and Regeneration, in consultation with the Head of Procurement and the Director of Governance (or their delegated officers), to carry out procurement processes in compliance with the Council’s Contract Procedure Rules and the Public Contract Regulations 2015 to seek suppliers for the delivery of the Net Zero Fund projects at Alex Lyon House and Honeysuckle House, and to subsequently enter into contracts covering design, consultancy services and construction works.

 

Reason:     To deliver the council’s ambitions for minimising the

energy bills of those residents facing financial challenges, supporting health and wellbeing, building the local green economy, and retrofit supply chains, and reducing carbon emissions in the city and to ensure the provisions of the Subsidy Control Act 2022 are complied with.

Report author: Anthony Dean

Publication date: 19/04/2024

Date of decision: 18/04/2024

Decided at meeting: 18/04/2024 - Executive

Effective from: 26/04/2024