Issue details
Contract Award: Hyper Hubs
Following the successful introduction of two
Hyper Hub locations, further projects are now ongoing to introduce
a further two Hyper Hubs at locations around the city. A
significant cost saving to both projects can be achieved by
duplicating the original HyperHub design, standardising the
equipment used, and aggregating the battery storage for an enhanced
ability to provide grid service.
To do this, officers are proposing a direct award of the design and
build contract to the supplier who designed and built the original
facilities. A decision is needed to make a direct award of the
construction contracts.
The Executive will be asked to
a) approve the direct award of the design and build contract for
Union Terrace HyperHub to Evo Energy Ltd. and to delegate authority
to the Director of Environment, Transport and Planning, in
consultation with the Director of Governance and the Head of
Procurement, to take such steps as are necessary to determine the
provisions of and enter into the resulting contracts; and
b) approve the direct award of the design and build contract for
the Askham Bar Hyper Hub to Evo Energy Ltd, subject to the suitable
resolution of outstanding legal conditions in respect of the site
and to delegate authority to the Director of Environment, Transport
and Planning, in consultation with the Director of Governance and
the Head of Procurement, to take such steps as are necessary to
determine the provisions of and enter into the resulting contracts;
and
c) approve a waiver of Rules 11.4 and 11.5 of the Council’s
Contract Procedure Rules in relation to the award of the
construction contracts for Union Terrace HyperHub and Askham Bar
HyperHub, as permitted to do so under Rule 26.1 of the Contract
Procedure Rules.
Decision type: Key
Decision status: For Determination
Wards affected: (All Wards);
Notice of proposed decision first published: 17/03/2025
Decision due: 06/05/25 by Executive
Lead member: Executive Member for Transport
Lead director: Director of Transport, Environment and Planning
Department: Directorate of Transport, Environment and Planning
Contact: Stuart Andrews, Transport Systems Project Manager Email: stuart.andrews@york.gov.uk Email: stuart.andrews@york.gov.uk.
Consultation process
Internal consultation with senior officers
from CYC Legal and Procurement Services.
No external consultation undertaken.
Consultees:
Internal consultation with senior officers from CYC Legal and
Procurement Services. Report to be reviewed by responsible CYC
officers with regards implications of the decision.
Equality Impact Assessment Completed?: Yes
Documents
- Contract Award: Hyper Hubs