Issue details
Riverside Path Improvement Scheme
The riverside path is a key route on the York
cycle network and is well used by pedestrians and cyclists,
connecting the west of the city with the city centre and the
Scarborough Bridge river crossing. The Riverside Path Improvement
Scheme focuses on the section of the path that runs from the
junction of Kingsland Terrace and Jubilee Terrace to Scarborough
Bridge.
This report outlines the preliminary scheme proposed for the
Riverside Path Improvement Scheme, providing an overview of its key
features and objectives.
This report provides a detailed summary of the feedback and
insights gathered during the public engagement process. It
highlights the concerns, suggestions, and general sentiment of
stakeholders.
In addition this report will also report the findings of a key
dependency to this project with regards to the Riverside Embankment
Structural Review (Appendix C), which evaluates the current
condition of the embankment and outlines the potential risks and
challenges, not only to the future of the embankments ongoing
stability, but also any associated impact to the Riverside Path
Improvements Scheme. This report seeks to facilitate a decision on
the embankment's future maintenance plan and any impact/interaction
with the proposed Riverside Path improvements.
The Executive Member will be asked to:
1. Approve progression of the Riverside Path Improvement scheme to
detailed design and construction, based on the scheme proposals and
preliminary design inclusions set out within the “Options
Analysis and Evidential Basis - Affordable Scheme” section of
this report
2. Provide direction on how to proceed regarding the risks
associated with the Riverside Embankment Stability issue and any
associated dependencies, as indicated within the “Options
Analysis and Evidential Basis – Riverside Embankment
Stability” section of this report and Appendix C, by
approving one of the following options:
i. Mandate a separately resourced and funded project with a brief
to identify the need for remedial works to improve Riverside
Embankment stability, generating recommendations for how this can
be achieved in a report which will be brought before a future
Executive Member Decision Session. Undertake detailed design work
for the Riverside Path improvement Scheme but delay construction
until the dependency on the Riverside Embankment Stability issue is
fully determined and resolved. Deliver both Projects in parallel
with delivery timelines to be aligned to provide one, robust,
future proofed solution.
ii. Take no action - noting the current condition of the embankment
has a negative impact on current use of the riverbank and is likely
to have impacts in the future on the Riverside Path Improvement
Scheme. Acknowledge the risk of the embankment instability
identified within the recent Riverside Path Embankment Stability
Report of 2024 (included at Appendix C) but proceed with the full
delivery (design and construction) of the Riverside Path
Improvement Scheme, understanding that any failure of the
embankment could directly affect the path and that construction of
the path may result in land movement which further deteriorates the
embankment stability and subsequent lifespan of both the path and
embankment.
3. To note in Appendix C, two remedial options are presented to
rectify the Riverside Embankment Stability. Remedial Option high
level cost estimates are in the region of circa. £500k to
£2.5m. The Riverside Path Project Team does not provide any
recommendations on which option to proceed with as further work is
required to understand the impact / risks of either option and the
eventual fully costed solution, taking into consideration any
associated third party costs (e.g. Environment Agency/Network
Rail.)
4. Approve the procurement of a Principal Contractor and Principal
Designer for the Riverside Path Improvement scheme and delegate
authority to the Director of Environment, Transport & Planning
(in consultation with the Director of Governance and the Head of
Procurement) to take such steps as are necessary to procure, award
and enter into the resulting contracts.
5. Delegate authority to the Director of Environment, Transport and
Planning to proceed with all necessary technical work, including
preparation of a detailed design, investigation and conduct of
diversions of statutory-undertakers apparatus to enable the works
in regard of the Riverside Path Improvement Scheme.
6. Delegate authority to the Director of Environment, Transport and
Planning to approve the final design to be delivered for the
Riverside Path scheme without the requirement for further EMDS
decision or public consultation unless scheme objectives or cost
tolerances cannot be met without significant alteration to the
preliminary design.
7. Approve the submission of any relevant planning application(s)
required to deliver the Riverside Path Improvement Scheme
affordable solution and delegate authority to the Director of
Environment, Transport and Planning to do so.
8. Approve the advertisement of an amendment to Traffic Regulation
order to introduce ‘No waiting at any time’
restrictions on Jubilee Terrace as part of the Riverside Path
Improvement Scheme.
9. Approve the advertisement of an amendment to Traffic Regulation
order to introduce ‘Prohibition of cycling’
restrictions on the Aldborough Way access ramp to the Riverside
Path as part of the Riverside Path Improvement Scheme.
Background documents
Active Travel Programme Update, Executive Member for Transport,
March 2023
https://democracy.york.gov.uk/ieDecisionDetails.aspx?AIId=64674
Decision type: Non-key
Decision status: Decision Made
Wards affected: (All Wards);
Notice of proposed decision first published: 10/02/2025
Decision due: 11/03/25 by Decision Session - Executive Member for Transport
Lead member: Executive Member for Transport
Lead director: Director of Transport, Environment and Planning
Department: Directorate of Transport, Environment and Planning
Contact: Shoaib Mahmood, Transport Project Manager Email: shoaib.mahmood@york.gov.uk Email: Shoaib.Mahmood@york.gov.uk.
Consultation process
Consultees: General Public and
internal/external stakeholders.
Equality Impact Assessment Completed?: Yes