Issue details
Update regarding the Recommission of the current York Reablement service
Purpose of Report: The Reablement Service was given approval by
Executive in October 2023 to proceed with a competitive tendering
process resulting in a new service being implemented from the 1
April 2024. The purpose of this report is to provide an update with
regards to the re-recommission of the Reablement Services and to
submit a new Procurement timeline that includes a 6-month
extension.
Original timelines and new timelines are outlined in the table
below:
Task Original timeline New timeline
Finalise specification 1st October 2023 31st January 2024
Issue tender to market 14th November 2023 27th February 2024
Tender evaluation Mid December 2023 4th April 2024– 24th May
2024
Contract award 6th January 2024 24th May 2024
Contract mobilisation Mid-January 2024 31st May 2024
New service commences 1st April 2024 30th September 2024
The Reablement Service is funded by the Better Care Fund and has
contributions from both the Council and the ICB. Additional
stakeholder engagement has been completed via workshops and
multi-agency meetings and this has enabled the specification to be
finalised whilst all partners made the necessary contribution to
the service specification.
The All-Age Commissioning team currently have two contracts for
Rapid Response Services from two different providers and they are
both not providing value for money and have different terms and
conditions. Seeking approval to combine both Rapid Response
services into one contract to simplify complex Reablement and Rapid
Response pathways. Furthermore, this option provides an opportunity
to secure significant benefits in terms of, obtaining better value
for money,
complying with The Council Procedure rules and reduces potential
challenge from providers within the market.
The Executive will be asked to approve the continuation of the
re-commission of York Reablement Services, with a 6-month extension
period to the previous timescales shared. Enabling the contract to
complete the tender process, contract award and mobilisation with a
new service in place for the 30 September 2024.
Approve the approach to combine both Rapid Response services and
contracts into one, as part of the Reablement Service. Tendering
both the Reablement and Rapid Response services as one opportunity
to the market via a tendering process.
The Council aims to give the same 28 days’ clear notice of non-key decisions as it does for key decisions, but in exceptional circumstances this may not be possible. It has not been possible to give 28 clear days’ notice of the intention to make this decision because the option to combine both Rapid Response services into one service, one contract and one tendering process is a recent development opportunity. This approach provides significant benefits in terms of achieving value for money, consistency of terms and conditions and ensures that the necessary approvals to proceed are obtained. The new timetable for the Reablement re-commission will enable the approach described above to be progressed and implemented.
Decision type: Key
Decision status: Decision Made
Wards affected: (All Wards);
Notice of proposed decision first published: 07/02/2024
This decision will be taken under urgency procedures.
Reason for urgency:
The option to combine both Rapid Response services into one service, one contract and one tendering process is a recent development opportunity. This approach provides significant benefits in terms of achieving value for money, consistency of terms and conditions and ensures that the necessary approvals to proceed are obtained. The new timetable for the Reablement re-commission will enable the approach described above to be progressed and implemented.
Decision due: 20/02/24 by Executive
Reason: It has not been possible to give 28 clear days’ notice of the intention to make this decision. Please open item for more information.
Lead member: Executive Member for Health, Wellbeing and Adult Social Care
Lead director: Corporate Director of Adult Services and Integration
Department: Directorate of Adult Services & Integration
Contact: Judith Culleton Email: abid.mumtaz@york.gov.uk Email: judith.culleton@york.gov.uk.
Consultation process
Additional stakeholder
engagement has taken place with Health and Social Care Partners and
has been utilised to update the service specification further for
the recommission of the Reablement Services.
The consultation will involve a survey being sent out to service
users, health professionals and other key stakeholders that will
inform the report to the Executive. A working group has also been
set up to look at the different options to recommission the York
Reablement Service. The outcome will be the implementation of an
efficient and effective commissioning model that will provide value
for money and is the best strategic fit for the delivery of our
Home First care and support pathway.
Consultees:
• York and Scarborough Hospital NHS Foundation Trust
• CYC Reablement Task and Finish Group.
• Reablement Responsive Care Pathway Working Group
• The York Multiple & Complex Needs Network –
added
• Age Friendly York Older Citizens Group - added
• NHS Humber and North Yorkshire Integrated Care Board
• Existing users of the reablement service.
• Age UK
• Healthwatch
• York Advocacy
• York Sensory Service
• Dementia Strategy Group
• Carers Strategy Group
• York CVS
• Other Stakeholders
Equality Impact Assessment Completed?: Yes
Decisions
Agenda items
- 20/02/2024 - Executive Update regarding the Recommission of the current York Reablement service 20/02/2024
Documents
- Update regarding the Recommission of the current York Reablement service
- Reg 10 - Update regarding the recommission of the current York Reablement service PDF 335 KB View as HTML (2) 8 KB