Issue details
Germany Beck Flood Alleviation Scheme
Purpose of Report: Flooding of properties in the Fordlands
community occurred in 2000 and has been managed through pumping
operations in 2012, 2015 and February 2020. Significant road
flooding occurs to Fordlands Road and the A19 in large flood events
leaving the Fordlands community isolated and causing significant
impact on many 1000’s of resident, commuter and tourist
journeys. A scheme to increase the resilience of the A19 to
flooding was delivered by the contractors completing the access
road to the Germany Beck housing development.
A holistic scheme has been identified that would provide a pumping
station to increase flood resilience to properties, maintain access
via Fordlands Road and further reinforce the works on the A19. A
funding package has been drawn together to develop this scheme,
design and appraisal works have been carried out to develop the
project further.
The scheme is being developed alongside the wider Environment
Agency led programme of works in the city, Executive have
previously agreed that the Executive Member for the Environment and
Climate Change would monitor and assure the delivery of the
programme. A paper taken to the Executive Member’s 12 August
2020 decision session resolved that the development of the next
stage of appraisal should be commenced – including detailed
design and all permissions including planning approval. A paper
will be brought to the Executive to update on all progress and
request approvals for the next stages of the project.
The Executive will be asked to:
· Endorse the work carried out to date.
· Approve the project to be taken through the planning process.
· Resolve to receive a future paper detailing the approach to the construction phase costs, procurement and delivery model and to approve the continued delivery of the project.
Decision type: Key
Decision status: Decision Made
Wards affected: Fulford and Heslington Ward;
Notice of proposed decision first published: 14/11/2022
Decision due: 15/12/22 by Executive
Lead member: Executive Member for Environment and Climate Change
Lead director: Corporate Director of Place
Department: Directorate of Place
Contact: Steve Wragg, Head of Highway Asset Management Email: steve.wragg@york.gov.uk Tel: 01904 553401.
Consultation process
Ongoing consultation with a wide range of internal departments to
develop the ongoing appraisal and design works with external
consultancy partners.
Ongoing consultation with external agencies and the community
during the development of the appraisal works
Equality Impact Assessment Completed?: EIA will be considered as part of the report.
Decisions
- 15/12/2022 - Germany Beck Flood Alleviation Scheme Update
Agenda items
- 15/12/2022 - Executive Germany Beck Flood Alleviation Scheme Update 15/12/2022
Documents
- Germany Beck Flood Alleviation Scheme