York Outer Ring Road – Phase 1 Dualling – Update on Progress and Proposed Enabling Works – Advanced Diversions of Statutory Undertakers’ Apparatus
Purpose of Report: The report will provide an update on progress of
the YORR Phase 1 Dualling project, namely the submission of a
planning application.
The main purpose of the report will inform Members that utility
apparatus exists on the footprint of the proposed scheme and will
set out a number of options for consideration.
The Executive will be asked to note progress on the scheme and
consider options and timing for enabling works.
Decision type: Key
Reason Key: Cabinet Decision - a 'Key Issue' - decision leading to savings or expenditure of £500,000 or above;
Decision status: Decision Made
Wards affected: Haxby and Wigginton Ward; Rawcliffe and Clifton Without; Rural West York Ward;
Notice of proposed decision first published: 18/05/2022
Anticipated restriction: Part exempt -
Explanation of anticipated restriction:
6. Information which reveals that the authority proposes:
(a) to give under any enactment a notice under or by virtue of which requirements are
imposed on a person; or
(b) to make an order or direction under any enactment.
Decision due: 16/06/22 by Executive
Lead member: Executive Member for Transport
Lead director: Corporate Director of Place
Department: Directorate of Place
Contact: Gary Frost, Major Transport Project Manager email: gary.frost@york.gov.uk; gary.frost@york.gov.uk.
Consultation process
A wide ranging consultation process was
undertaken in autumn 2020.
Equality Impact Assessment Completed?: EIA will be considered as part of the report.
Decisions
Agenda items
- 16/06/2022 - Executive York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm) 16/06/2022
Documents
- York Outer Ring Road – Phase 1 Dualling – Update on Progress and Proposed Enabling Works – Advanced Diversions of Statutory Undertakers’ Apparatus