The purpose of this report is to consider the potential sites for a
new Haxby Station and recommend a single preferred site to be taken
forward for further development.
Executive Members will be asked to, subject to previous approvals
at Executive on 30 September 2021, approve a preferred single site
to take forward for further development as the potential location
of the new Haxby Station.
This item will be deferred to the 18 November 2021 Executive Meeting. Following the September Executive meeting the Council has been busy finalising the purchasing of the land. However, in the short timeframe between the Executive approving the purchase and the need for reports for the next meeting being published, the Council has not been able to finish all the necessary legal processes in time for a report to go to October’s meeting. The potential for this postponement was discussed at the September Executive meeting, given the short time available to finalise the acquisition before the publication of reports for the next meeting. Work continues on the project and is not expected to impact the timelines for the wider Haxby station project.
This item has been deferred to the 9 December Executive meeting. Reason: To enable all legal processes to be finalised.
Decision type: Non-key
Decision status: Decision Made
Wards affected: Haxby and Wigginton Ward;
Notice of proposed decision first published: 23/08/2021
Level of Risk: 04-08 Regular monitoring required;
Decision due: 09/12/21 by Executive
Reason: This item has now been defered from the 14 October 2021 Executive meeting, please open this item for further details.
Lead member: Executive Member for Transport
Lead director: Corporate Director of Place
Department: Directorate of Place
Contact: Richard Holland Email: richard.holland@york.gov.uk Email: Richard.Holland@york.gov.uk.
Consultation process
Public consultation on the principle of a
Station at Haxby was undertaken locally during May 2020, as part of
the bid process for DfT New Station Funding.
Further public consultation expected to be undertaken prior to
progressing to the next delivery stage.
Consultation will be undertaken, at the next development, stage
with:
• Local residents of Haxby & Wigginton.
• Network Rail, as partner organisation in this project.
Equality Impact Assessment Completed?: To be completed.