York 5 Year Plan Flood Scheme Update

Purpose of report: City of York Council is working in close partnership with the Environment Agency in the development of the York 5 Year Plan to update and renew flood defences in the city. This report will provide an update on the progress so far, the key outputs that have been produced and the programme of further works.

The Executive Member is asked to: Review and debate the report and agree to recommendations and next steps.

Consideration of this item has been deferred from 5 June to 3 July 2017, in order to allow the authority to invite the Environment Agency to attend and join in the public discussion.

 

Unfortunately the Environment Agency are unable to take part in any pubic discussions with members during purdah.

Decision type: Non-key

Decision status: Decision Made

Wards affected: Acomb Ward; Bishopthorpe Ward; Clifton Ward; Fishergate Ward; Fulford and Heslington Ward; Haxby and Wigginton Ward; Heworth Ward; Heworth Without Ward; Holgate Ward; Huntington and New Earswick Ward; Osbaldwick and Derwent Ward; Rawcliffe and Clifton Without; Strensall Ward; Westfield Ward;

Notice of proposed decision first published: 10/04/2017

Decision due: 03/07/17 by Executive Member for Environment

Lead member: Executive Member for Environment

Lead director: Corporate Director of Economy and Place

Department: Directorate of Economy and Place

Contact: Steve Wragg, Head of Highway Asset Management Email: steve.wragg@york.gov.uk Tel: 01904 553401 Tel No. 01904 553401.

Consultation process

Links to the emerging Environment Agency York 5 Year Plan work will be made.

Making Representations: Please contact the report author.