Issue details
Crichton Avenue scheme completion and petition request
Purpose of Report: This report is in response
to a petition received requesting demarcation of the bridge section
within the Crichton Avenue cycle improvement scheme and to report
the completion of the scheme. The final snagging measures plus
trialling of the demarcation should have been implemented prior to
this meeting but a verbal update will confirm this at the meeting.
The Executive Member is asked to: Note the successful completion of
the Crichton Avenue scheme and to report residents concerns raised
in the petition delivered by the local ward councillor have been
met through a trial as agreed with the Department for
Transport.
Decision type: Non-key
Decision status: Decision Made
Wards affected: Clifton Ward;
Level of Risk: 01-03 Acceptable;
Decision due: 07/12/10 by Decision Session - Executive Member for City Strategy
Decision due: 07/12/10 by Executive Member for City Strategy
Lead member: Executive Member for City Strategy
Lead director: Corporate Director of Economy and Place
Department: Directorate of Economy and Place
Contact: Graham Titchener Tel: 01904 551330; Email: bill.woolley@york.gov.uk graham.titchener@york.gov.uk.
Consultation process
Please contact report author.
Consultees
Department for Transport and internal officers
only.
Making Representations: Please contact report author.
Equality Impact Assessment Completed?: N/A
Background4: N/A
Decisions
- 07/12/2010 - Crichton Avenue Cycle Scheme - Completion
Agenda items
- 07/12/2010 - Decision Session - Executive Member for City Strategy Crichton Avenue Cycle Scheme - Completion 07/12/2010
Documents
- Committee Report for Crichton Avenue scheme completion and petition request