James Street Link Road Phase 2 modelling refresh
Purpose of report: The report will consider
the study undertaken by Halcrow to re-examine the modelling
undertaken by Jacobs in 2003 in order to determine if and when
James Street Link Road Phase 2 should be constructed.
The report will also present the results of surveys undertaken on
various streets in the Heworth area to assess the increase in
traffic and extent of violations of traffic orders (for turning
restrictions etc) in the area.
The modelling will provide a commentary on the optimum time for
constructing the southern section of Phase 2 of the link road to
maximise the financial benefits and confirm, or ortherwise, if it
will coincide with the anticipated delivery programme for a private
development, off Layerthorpe, through which a section of the link
road will pass. The conditions of the Outline Planning Consent for
the development require the developer to implement this section of
Link Road. Timescale is dependent on the modelling output.
Members are asked to: Note the need for an optimum time for
constructing the southern section of James Street Link Road Phase 2
and decide whether the Council should either pursue its
construction by the developer, or instruct further work to be
undertaken to provide an estimate for its construction by the
council.
Decision type: Non-key
Decision status: Implemented
Wards affected: Heworth Ward;
Decision due: 20/10/08 by Executive Member for City Strategy
Lead member: Councillor Steve Galloway cllr.stephengalloway@york.gov.uk
Lead director: Corporate Director of Economy and Place
Department: Directorate of Economy and Place
Contact: Ian Stokes, Development Officer Email: ian.stokes@york.gov.uk.
Consultation process
N/A
Making Representations: N/A
Decisions
Agenda items
- 20/10/2008 - Executive Members for City Strategy and Advisory Panel James Street Link Road Phase 2 - Stage 1 Traffic Forecast Refresh 20/10/2008
Documents
- Committee Report for James Street Link Road Phase 2 modelling refresh