Access York Phase 1 Park & Ride development - Programme and Consultation Plan
- 01/07/2008 - Published in plan, 29 June to 28 October 2008
- 15/07/2008 - Published in plan, 15 July to 14 November 2008
- 18/07/2008 - Action: Meeting of Political Group Leaders ; status: created
- 28/07/2008 - Action: If required, this item will be considered at a pre Executive meeting of the Strategic Policy Panel ; status: created
- 29/07/2008 - Agenda item, Executive - for meetings from 03/06/00 to 26/04/11 Access York Phase 1 Park & Ride development - Programme and Consultation Plan 29/07/2008
- 29/07/2008 - Published decision: Access York Phase 1 Park & Ride development - Programme and Consultation Plan
- 31/07/2008 - Call-in period expired: Access York Phase 1 Park & Ride development - Programme and Consultation Plan
- 01/08/2008 - Published in plan, 29 July to 28 November 2008
- 04/08/2008 - Agenda item scheduled, Corporate Services, Climate Change and Scrutiny Management Committee (Calling In)
- 04/08/2008 - Action: After the Executive and if required, this item may be considered at a meeting of the Strategic Policy Panel ; status: created
- 26/08/2008 - Action: 1. Commence project, and include progress report to Executive on Forward Plan. Jane Benson ; status: completed late
- 26/08/2008 - Action: 4. Begin consultation on A59 site, including subway. Jane Benson ; status: completed late
- 26/08/2008 - Action: 5. Begin consultation on the four Wigginton Rd sites (including south-west junction). Jane Benson ; status: completed late
- 26/08/2008 - Action: 2. Set up Project Board and Project Team. Jane Benson ; status: completed late
- 26/08/2008 - Action: 3. Begin consultation on Askham Bar site. Jane Benson ; status: completed late
- 26/08/2008 - Action: 6. Make arrangements to keep Ward Members, Parish Councils and residents informed. Jane Benson ; status: completed late