Centre of Excellence for Disabled Children

19/06/2019 - Centre of Excellence for Disabled Children and their Families in York

Resolved:  (i)      That an increase of £250,000 to the budget, to be funded by a virement from uncommitted resources within the Education Basic Need capital budget, be approved.

 

Reason:     To ensure that there is adequate contingency and reduce the risk of costs exceeding the agreed budget in the construction phase.

 

(ii)      That authority to appoint a Contractor to carry out the works be delegated to the Director of Children, Education and Communities, subject to the project being deliverable within the available budget.

 

Reason:     In order to align the programme with that of the Lincoln Court development and enable a shared contractor to deliver both projects concurrently, thus achieving cost efficiencies.

 


 