Q3 2018-19 Capital Programme Monitor

15/02/2019 - Capital Programme - Monitor 3 2018/19

Resolved:  (i)      That the 2018/19 revised budget of £106.291m, as set out in Table 1 at paragraph 6 of the report, be noted.

 

                   (ii)      That the re-stated capital programme for 2018/19-2022/23, as set out in Table 2 at paragraph 58 and detailed in Annex A, be noted.

 

                   (iii)     That the use of £120k from capital contingency to the Mansion House scheme, as set out in paragraphs 56-57, be approved.

 

Reason:     To enable the effective management and monitoring of the council’s capital programme.


 