Issue - decisions
York Central
14/07/2016 - York Central
Resolved: (i) That the responses to the informal consultation
on “Seeking your views to guide development” be noted.
(ii) That the approach to establish a York Central
Community Forum as an integral part of the consultation process for the site be noted.
(iii) That the progress over the past six months to
inform the emerging York Central Planning Policy and deliver the York Central site be noted.
(iv) That a loan of £2.55m from Leeds City Region
(LCR) Local Growth Fund as an element of the funding proposals for York Central be agreed in principle.
(v) That the Director of Customer and Business
Support Services, in liaison with the Leader, be delegated to agree the terms for a Funding Agreement with Leeds City Region (LCR) Local Enterprise Partnership (LEP).
(vi) That a further draw down from the £10m
allocation of £0.55m be agreed in order to fund the immediate site preparation works outlined in the report.
Reasons: (i) To ensure issues raised from the
consultation are taken account of in developing the Planning Framework SPD.
(ii) To ensure the views of the local community
are represented as the site progresses.
(iii) To ensure that a development scheme for
the York Central site can be delivered.
(iv) – (vi) To enable timely progress on the York Central project.