Access York Phase 1 - Submission of Full Approval Application to the Department for Transport

08/01/2013 - Access York Park and Ride Funding Application

RESOLVED:      That Cabinet agree to approve the following in relation to this scheme:

i)             Submission of the Full Approval Application to the Department for Transport.

 

ii)            An increase in the local contribution to the scheme of up to £750k from the Economic Infrastructure Fund and a re-profile of the Capital Programme where necessary.

 

iii)          Commencement of advance site clearance.

 

iv)          Commencement of advance utility diversions.

 

v)           Delegation of the acceptance of the Most Economically Advantageous Tender to the Director of City and Environmental Services in consultation with the Cabinet Member for Transport, Planning and Sustainability.

 

REASON:           To enable the delivery of the Access York project to programme.

 

 


 