2012/13 City and Environmental Services Capital Programme Consolidated Report
13/08/2012 - 2012/13 City and Environmental Services Capital Programme Consolidated Report
RESOLVED:
That the Cabinet Member for Planning, Transport and Sustainability:
i. Approved the carryover schemes and adjustments set out in Annexes 1 and 2.
ii. Approved the increase to the 2012/13 CES capital programme budget, subject to the approval of the Cabinet.
iii. Noted the outturn figures and scheme progress set out in Annexes 3 and 4 for the 2011/12 capital programme.
iv. AQ03/11 Electric Vehicle Charging Points – Carry over £30k underspend from 11/12 to increase 12/13 budget to £60k by increasing overprogramming.
v. CY06/12 Cycle Parking – Increase allocation by £25k to £40k (overprogramming increased) to provide additional cycle parking in city centre to match rising demand.
Reason: To enable to effective management and monitoring of the council’s capital programme.