Issue - decisions

2009/10 Capital Programme Outturn

21/07/2010 - Capital Programme Out-turn 2009/10 and Revisions to the 2010/11-2014/15 Programme

RESOLVED:(i)         That the 2009/10 capital out-turn position be noted and that the requests for slippage to and from the 2010/11 capital programme be approved.

 

                        (ii)        That the re-stated 2010/11 to 2014/15 programme, as summarised in Table 4 at paragraph 54 of the report and detailed in Annex 1, be approved.

 

                        (iii)       That the use of £25k contingency to support Strensall Parish Council in seeking to provide youth facilities in Strensall be approved, subject too the receipt by Officers of the business plan showing the scheme and partners.

 

REASON:      To allow the continued effective financial management of the capital programme from 2010/11 to 2014/15.


 