Agenda item
Germany Beck Pumping Station
Minutes:
1. Germany Beck Pumping Station – Mark Henderson CYC Flood Manager
Project Overview:
- Mark Henderson introduced himself and provided an update on the Germany Beck flood management project. He welcomed questions during or after the presentation.
Location & Infrastructure:
- Germany Beck and the associated pumping station were highlighted. Downstream impacts affect the A19 and local SSSI areas.
Flood Impacts:
- High water levels in Germany Beck can back up, causing flooding at Fordlands Road and Fordlands Crescent.
- In severe cases, temporary infrastructure like a scaffolded bridge is required to maintain access.
- Surface water drainage from residential areas (e.g., Fordlands Estate) contributes to local flooding, with approximately 300+ properties affected.
- Historical context: Around 20–23 properties were flooded in 2015.
Scheme Justification:
- Main drivers: prevent road blockages at Fordlands Road, reduce residential flooding at Fordlands Crescent, and manage tunnel drain overflow.
- Economic and community benefits: preventing flooding protects homes, ensures road accessibility (A19 carries ~16,000 vehicles/day), and supports broader local economic impacts.
Funding:
- Central government and City of York Council are co-funding the scheme based on the business case demonstrating flood risk reduction and economic benefits.
Pumping Station Function:
- The pumping station will draw water from Germany Beck when high water levels cause hydraulic locking at the Ings.
- Water will be pumped through an offline system into a wet well and then through a new culvert under the A19 to manage flow.
- Downstream risk is minimal; modelling shows the pumped volume is negligible relative to the total water body.
Project Timeline & Procurement:
- Specialist contractor procurement planned for April–May next year; contract to be approved by August.
- Site mobilisation and planning condition discharges will occur before work starts.
- Construction is expected to begin in autumn next year.
Budget:
- Indicative cost: ~£4.5 million, including 25–30% contingency. Final cost depends on market responses.
Sequence of Works:
- Key elements: pumping station, kiosk/pump panel, culvert, downstream headwall, and structural changes to upstream/downstream areas.
- Work may be phased; exact sequencing will be determined once the contractor is appointed.
Temporary Access & Storage:
- Parts of the park will be temporarily cordoned off for access, equipment storage, and work along the bank and parish field.
- Access will be via Fordlands Road. Temporary disruptions are expected, but benefits of the project are expected to outweigh short-term inconveniences.
Project Timeline:
- Work expected to start in autumn 2026 (following mobilisation).
- Duration estimated at around one year, slightly longer than the original 64-week business case projection.
- Design refinements may occur once the contractor begins work, similar to adjustments made after an architect hands over to a builder.
- Project completion anticipated by autumn 2027.
Constraints & Impacts:
- Key considerations include ecology, landscape, archaeology, and A19 impacts.
- Ecological protections:
- Areas of ecological importance (SSSI/triple S) identified downstream of A19.
- Pumping station designed to be eel-friendly, using slower, larger impellers (similar to an Archimedes screw) to allow safe passage of eels.
- Water vole surveys conducted in September; further surveys planned in April.
Ecological Surveys & Protections:
- Spring 2025 surveys planned for water voles; mitigation measures and licenses required if present.
- No signs of otters; nesting birds will be protected.
- Tree management: some trees may be removed, others retained or replaced, with protections for roots.
- Invasive species (Himalayan balsam, waterweed) will be carefully managed to prevent spread.
- Additional ecological surveys needed: bats, trees, and habitats, as previous surveys (2021) are now outdated.
- Construction will follow detailed Environmental Management Plans and method statements to minimise ecological impact.
Archaeology:
- Work with local and county archaeologists to manage potential archaeological finds, including Battle of Fulford area.
- Excavation for the pumping station may uncover historical materials, which will be sifted with volunteer involvement.
- Archaeological mitigation and recording will be integrated into the construction process.
Q&A – Germany Beck Flood Management
Archaeology & Project Timelines:
- Significant finds during excavation will be removed and investigated but will not delay construction. Archaeologists will work alongside contractors.
A19 & Construction Impacts:
- Options for culvert construction under the A19 include partial road closure or thrust boring; final approach pending geotechnical studies and traffic modelling.
- Work involves significant construction due to peat layers and foundation requirements.
Design & Environmental Considerations:
- Pumping station design largely fixed, with minor tweaks possible for eel-friendly pumps and sluices.
- Landscaping and tree replacement plans in place; temporary use of the playing field will not affect newly planted areas.
Flooding & Access Concerns:
- Concerns raised about pedestrian and vehicle access during floods, particularly for carers and emergency access.
- Current interim measures (scaffold bridges, pumps) will remain until pumping station is operational.
- Possibility of additional temporary structures or increased pump capacity to manage water levels is being explored.
Tunnel Drain & Sewer System:
- Pumping station will maintain free flow in Tunnel Drain, preventing backflow and flooding of properties.
- Some foul water misconnections may exist; issue to be investigated with Yorkshire Water.
- Maintenance responsibility for culverted sections is complex; currently managed by Internal Drainage Board, with cost and liability considerations.
Funding & Legacy Issues:
- Project funded by City of York Council and central government; efforts ongoing to minimise cost to taxpayers.
- Historical development (e.g., Persimmon Homes) contributed to some existing flood issues; responsibility outside development boundaries is limited.
- Environmental improvements will be made where the pumping station impacts SSSI areas, but no wider remediation beyond the project area.
Additional Notes:
- Residents’ concerns about SSSI mitigation, flood season impacts, and temporary access acknowledged; further updates to be communicated as information becomes available.
- Mark Henderson emphasised transparency, cost-effectiveness, and collaboration with other agencies.