Active Travel Programme Update
Meeting: 21/03/2023 - Decision Session - Executive Member for Transport - Expired (Item 72)
72 Active Travel Programme Update PDF 563 KB
This report provides an update on the progress of the Active Travel Programme and asks the Executive Member to note this update.
Additional documents:
- Annex A - ATF4 Bid Invitation Letter, item 72 PDF 189 KB
- A. Overall Programme, item 72 PDF 1 MB
- Acomb Road, item 72 PDF 778 KB
- Fulford Road Frederick House, item 72 PDF 732 KB
- Haxby Station to Strensall Village, item 72 PDF 1 MB
- Jubilee Terrace to Scarborough Bridge, item 72 PDF 893 KB
- Manor Lane Shipton Road, item 72 PDF 851 KB
- Monkgate Roundabout, item 72 PDF 843 KB
- People Streets Ostman Road, item 72 PDF 926 KB
- Tang Hall Lane, item 72 PDF 835 KB
- Annex C - Active Travel Programme Summary v1.0 09032023, item 72 PDF 347 KB
- Annex D - ATF4 Bid Scheme summary v1.0 24022023, item 72 PDF 358 KB View as HTML (72/13) 23 KB
- Annex E - Project Outline - A19 Phase 1 Interventions v1.0 21022023, item 72 PDF 351 KB View as HTML (72/14) 30 KB
- Annex F - Riverside Path Consultation Report - for issue, item 72 PDF 2 MB
- Annex G - Riverside Path Feasibility Study Report March-23, item 72 PDF 10 MB
- Annex H - Riverside Path EIA, item 72 PDF 673 KB View as HTML (72/17) 89 KB
- Wheldrake Heslington Path, item 72 PDF 789 KB
Decision:
Resolved:
i. Noted the update on the progress of the Active Travel Programme contained within this report;
Reason: To provide information to the public and the Member on the current status of the Active Travel Programme.
ii. Noted the update contained within this report covering the recent ATF4 bid submission;
Reason: To provide information to the public regarding the request for funding submitted to Active Travel England.
iii. Approved the “A19 Phase 1 Interventions” Project Outline (Option 1).
It should be noted that a decision on the implementation of the crossing is not being sought at this time. A further public decision on the proposals will be presented after feasibility work has been completed;
Reason: To agree the scope of the project, to ensure it is aligned with stakeholder expectations.
iv. Noted the results of the Riverside Path Consultation, the initial feasibility work undertaken by Aecom and the current funding gap;
Reason: To understand the options for improving the route and the priorities for the local residents.
v. Approved the progression of Option 2 to deliver the scheme on a phased basis commencing with the higher priority affordable items (lighting & CCTV) and undertake further development work within the current budget.
Reason: Progressing with Phase 1 of the path upgrade (lighting and CCTV) allows progress to be made on-site whilst further work is undertaken on the feasibility of the full scheme.
Minutes:
Officers introduced the Active Travel Programme update and confirmed that the existing priorities for the programme had been agreed by the Executive in 2022. They noted that allocations for tranche 4 Active Travel funding was likely to be lower than previous allocations due to central government budget cuts. It was noted that many schemes in the LCWIP were at an early stage which was why some lower priority schemes which were ready for consultation were currently being progressed. Officers confirmed that in conversations with Active Travel England that bids should be separated to focus on those that are ready for delivery and those that were longer term schemes.
The Executive Member considered a number of schemes in the programme including the Riverside Path which was raised during public participation. Officers confirmed that residents had been consulted with responses focusing on additional lighting for the path as well as raising and widening the path to reduce the number of days the path was unpassable due to flooding. Officers confirmed that they were recommending to deliver in stages focusing on affordable parts of the scheme such as lighting and CCTV. Should the Council not be successful in getting sufficient funding to deliver the other parts of the scheme it was confirmed that a new report would be brought to a Transport Decision Session for consideration how to move forward. Lighting underneath Scarborough Bridge was discussed and the Executive Member asked that it be included in work on the Riverside Path. Signage was also discussed around Scarborough Bridge.
Resolved:
i. Noted the update on the progress of the Active Travel Programme contained within this report;
Reason: To provide information to the public and the Member
on the current status of the Active Travel Programme.
ii. Noted the update contained within this report covering the recent ATF4 bid submission;
Reason: To provide information to the public regarding the
request for funding submitted to Active Travel
England.
iii. Approved the “A19 Phase 1 Interventions” Project
Outline (Option 1). It should be noted that a decision on the implementation of the crossing is not being sought at this time. A further public decision on the proposals will be presented after feasibility work has been completed;
Reason: To agree the scope of the project, to ensure it is
aligned with stakeholder expectations.
iv. Noted the results of the Riverside Path Consultation,
the initial feasibility work undertaken by Aecom and
the current funding gap;
Reason: To understand the options for improving the route
and the priorities for the local residents.
v. Approved the progression of Option 2 to deliver the scheme on a phased basis commencing with the higher priority affordable items (lighting & CCTV) and undertake further development work within the
current budget.
Reason: Progressing with Phase 1 of the path upgrade
(lighting and CCTV) allows progress to be made onsite whilst further work is undertaken on the
feasibility of the full scheme.