Issue - meetings
2007/08 Capital programme Update
Meeting: 26/03/2007 - Executive Members for City Strategy and Advisory Panel (Item 107)
107 Proposed 2007/08 City Strategy Capital Programme PDF 118 KB
This report sets out the details of the proposed City Strategy Capital Programme for 2007/08, and asks the Executive Member for City Strategy to approve the proposed programme.
Additional documents:
Decision:
Advice of the Advisory Panel
That the Executive Member for City Strategy be advised to:
(i) Accept the increased cost of the Moor Lane roundabout scheme identified in paragraph 12 of the report : a total scheme cost of £3.5 m;
(ii) Approve the proposed 2007/08 City Strategy Capital Programme as set out in the report.
Decision of the Executive Member for City Strategy
RESOLVED: That the advice of the Advisory Panel be accepted and endorsed.
REASON: (i) To enable the delivery of the scheme and achieve the benefits to road safety and accessibility in the area;
(ii) To implement the council’s transport strategy as set out in York’s second Local Transport Plan.
Minutes:
Members considered a report which set out the details of the proposed City Strategy Capital Programme for 2007/08, and requested approval for this proposed programme.
The report detailed the schemes within the Local Transport Plan.
Members discussed the Fulford Road Multi-Modal scheme, Park & Ride City Centre Bus Stop upgrades, BLISS (Bus Location and Information Sub-System), and the provision of bus timetables.
Advice of the Advisory Panel
That the Executive Member for City Strategy be advised to:
(i) Accept the increased cost of the Moor Lane roundabout scheme identified in paragraph 12 of the report : a total scheme cost of £3.5 m;
(ii) Approve the proposed 2007/08 City Strategy Capital Programme as set out in the report;
(iii) That a report be brought to Members at the June meeting of this committee on BLISS.
Decision of the Executive Member for City Strategy
RESOLVED: That the advice of the Advisory Panel be accepted and endorsed.
REASON: (i) To enable the delivery of the scheme and achieve the benefits to road safety and accessibility in the area;
(ii) To implement the council’s transport strategy as set out in York’s second Local Transport Plan.