Capital Programme Monitor 1
Meeting: 29/08/2019 - Executive (Item 35)
35 Capital Programme - Monitor 1 2019/20 PDF 307 KB
The Corporate Finance & Commercial Project Manager to present a report which sets out the projected outturn position of the council’s capital programme for the 2019/20 financial year, along with requests to re-profile budgets to or from current and future years.
Additional documents:
Decision:
Resolved: (i) That the 2019/20 revised budget of £205.478, as set out in Table 1 at paragraph 6 of the report, be noted.
(ii) That the re-stated capital programme for 2019/20 – 2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted.
(iii) That approval be given to increase the gross budget for the Assistance to Older & Disabled People programme by £200k, funded by a revenue contribution from the Housing Revenue Account (HRA), as detailed in paragraph 25.
(iv) That the contract award outlined in paragraphs 57 to 62 be approved.
Reason: To enable the effective management and monitoring of the council’s capital programme.
Minutes:
[See also under Part B]
The Corporate Finance & Commercial Procurement Managerpresented a report which set out the projected out-turn position of the council’s capital programme for the 2019/20 financial year, along with requests to re-profile budgets to and from current and future years.
A decrease of £65.816m on the current approved programme was reported, resulting in a revised programme of £205.478m. Variances against each portfolio area were set out in Table 1 at paragraph 6 of the report and detailed in paragraphs 8 to 62. Approval was sought for:
· An increase of £200k in the budget for the Assistance to Older & Disabled People scheme to cover a backlog of adaptations carried over from 2017/18, funded from an HRA revenue contribution; and
· The award of a 5 year contract, totalling £1.1m, to deliver an essential Firewall software upgrade, funded from the existing budget set aside for this purpose.
Resolved: (i) That the 2019/20 revised budget of £205.478, as set out in Table 1 at paragraph 6 of the report, be noted.
(ii) That the re-stated capital programme for 2019/20 – 2023/24, as set out in Table 2 at paragraph 17 and detailed in Annex A, be noted.
(iii) That approval be given to increase the gross budget for the Assistance to Older & Disabled People programme by £200k, funded by a revenue contribution from the Housing Revenue Account (HRA), as detailed in paragraph 25.
(iv) That the contract award outlined in paragraphs 57 to 62 be approved.
Reason: To enable the effective management and monitoring of the council’s capital programme.