Issue - meetings
Capital Programme
Meeting: 30/06/2016 - Executive (Item 16)
Capital Programme Outturn 2015/16 and Revisions to the 2016/17 - 2020/21 Programme
Decision:
Recommended: That Council agree the restated 2016/17 to 2020/21 programme of £221.594m as summarised in Table 3 and detailed in Annex A of the report.
Reason: To enable the effective management and monitoring of the Council’s capital programme.
Minutes:
[See also Part A minute]
Consideration was given to a report which set out the capital programme outturn position, including any under or overspends, overall funding of the programme and an update on the future years programme.
It was noted that the report showed an outturn of £41.505m compared to an approved budget of £51.538, an overall variation of £10.033m, made up from requests to reprofile budgets and adjustments to schemes detailed in the report.
The variances for individual department were also reported together with the restated capital programme at Table 3.
Officers reported on the capital schemes both completed and underway to deliver the Council’s priorities.
Recommended: That Council agree the restated 2016/17 to 2020/21 programme of £221.594m as summarised in Table 3 and detailed in Annex A of the report. 1.
Reason: To enable the effective management and monitoring of the Council’s capital programme.