Capital Programme - Monitor 3 2015/16

Meeting: 11/02/2016 - Executive (Item 118)

Capital Programme - Monitor 3 2015/16

Decision:

 

 

Recommended: That Council agree a decrease in the 2015/16 programme of£40.654m as detailed in the report and contained in Annex A.

 

Reason:              To enable the effective management and monitoring of the Council’s capital programme.

 

Minutes:

[See also Part A minute]

 

Members considered a report which informed them of the likely outturn position of the 2015/16 Capital Programme including any adjustments and requests to re-profile budgets between years.

 

The current approved Capital Programme for 2015/16 was £94.389m, following amendments previously reported to Executive and Council. A decrease of £40.654m, details of which were set out in the monitor report and had resulted in a revised Capital Programme budget of £51.538m, the majority of which had due to re-profiling of budgets to future years. Offsetting this had been a net increase of £229k mainly due to an increase from the Better Bus Area Fund of £308k from external contributions.

 

The variances against each portfolio area, together with a summary of the key exceptions and implications on the capital programme, were set out at paragraphs 9 to 42 and at Annex A of the report. A summary of the revised 5 year Capital Programme incorporating the proposed changes highlighted in the report were shown at Table 2 and the proposed financing at Table 3.

 

Following discussion it was

 

Recommended: That Council agree a decrease in the 2015/16 programme of£40.654m as detailed in the report and contained in Annex A. 1.

 

Reason:              To enable the effective management and monitoring of the Council’s capital programme.

 


 