Lendal Bridge Sub-Station, Wellington Row

Minutes:

The Shadow Executive considered a report which was listed as item 10 on the agenda for the Executive meeting on 25 July, at page 121.  The report asked Members to consider the future use of a former sub-station at Wellington Row, adjoining Lendal Bridge.

 

Having discussed the issues set out in the report, the following comments were agreed:

           

The Shadow Executive:

·  Was concerned that there was no evidence that the Council’s protocol on disposal of assets had been fully followed (ie: internal consultation with departments) to ascertain if there were any alternative uses for the site.

·  Supported Option B.

 

RESOLVED:(i) That the Executive be asked to take the above comments into account when considering this item.

 

                        (ii)        That the item not be called in.


 