Highway Maintenance, Advanced Design on programme for 2015-16
Meeting: 11/12/2014 - Decision Session - Executive Member for Transport - Expired (Item 33)
33 Highway Maintenance, Advance Programme for 2015-16 PDF 123 KB
This report informs the Cabinet Member on the preparation of the provisional highway maintenance surfacing programme. It recommends and seeks approval to begin advanced design for a list of schemes in each category of work.
Additional documents:
Decision:
Resolved: That the Cabinet Member agreed to:
(i) Maintain the split in funding between footways and roads on a 40/60 basis.
(ii) Approve the provisional programme of work as attached at Annexes 1 and 2 of the report.
Reason: To allow for preparation of a programme of work for 2015-16.
Minutes:
The Cabinet Member considered a report which outlined the provisional highway maintenance surfacing programme for 2015-2016. The report recommended and sought approval to begin advanced design for a list of schemes in each category of work.
Resolved: That the Cabinet Member agreed to:
(i) Maintain the split in funding between footways and roads on a 40/60 basis.
(ii) Approve the provisional programme of work as attached at Annexes 1 and 2 of the report.
Reason: To allow for preparation of a programme of work for 2015-16.