Q1 Capital Programme Monitor

Meeting: 09/09/2014 - Executive (Item 29)

29 Capital Programme Monitor One 2014/15 pdf icon PDF 153 KB

This report sets out the projected capital programme outturn position for 2014/15 including any under/ over spends and adjustments, along with requests to re-profile budgets to/from current and future years.

 

Additional documents:

Decision:

Resolved:  That Cabinet agree to:

 

(i)           Note the 2014/15 revised budget of £76.319m as set out at paragraph 5 and Table 1 of the report.

(ii)          Note the restated capital programme for 2014/15 – 2018/19 as set out at paragraph 28, Table 2 and detailed in Annex A of the report.

Reason: To enable the effective management and monitoring of the Council’s capital programme.

 

 

 

Minutes:

[See also Part B minute]

 

Members considered a report which set out details of the Council’s projected capital programme outturn position for 2014/15, including any under/over spends and adjustments, together with requests to re-profile budgets to/from current and future years.

 

It was noted that the current 2014/15 capital programme, as approved by Council and updated in July was £83m, with current monitor showing a decrease of £6.912m resulting in a revised capital programme of £76.319m, the majority of which was attributable to the re-profiling to future years budgets and the remainder to a reduction in government grants.

 

The variances in each portfolio were shown at Table 1 of the report and a summary of the key exceptions and implications on the capital programme reported in paragraphs 8 to 26. Revisions to the 5 year programme were also reported together with details of funding for future years to 2018/19.

 

The Leader highlighted work proposed on the city’s War Memorials and to the extensive capital works set out in Annex A to the report. Members also referred to the demographic pressures on local schools and the need for good sustainable planning for the future needs of children in the city.

 

Resolved:  That Cabinet agree to:

 

(i)           Note the 2014/15 revised budget of £76.319m as set out at paragraph 5 and Table 1 of the report.

(ii)          Note the restated capital programme for 2014/15 – 2018/19 as set out at paragraph 28, Table 2 and detailed in Annex A of the report.

Reason: To enable the effective management and monitoring of the Council’s capital programme.

 

 

 


 