Capital Programme - Monitor 3 2013/14
Meeting: 11/02/2014 - Executive (Item 104)
Capital Programme Monitor 3 2013-14
Decision:
Recommended: That Council agree the adjustments in the Capital programme of a decrease of £11.659m in 2013/14 as detailed in the report and contained in Annex A.
Reason: To enable the effective management and monitoring of the Council’s capital programme.
Minutes:
[See also Part A minute]
Consideration was given to a report which set out the projected capital programme outturn position for 2013/14, including any under/overspends and adjustments and requests for re-profiling of budgets.
With the 2013/14 capital programme budget at £72.573k, this monitor had shown a decrease of £11.659m resulting in a revised capital programme of £60.914m. The net decrease being made up of a reprofiling of schemes of £12.136m to 2014/15 and an increase of budgeted schemes at £477k. The variances against each profile area and a summary of the exceptions and implications on the programme were reported at Table 1, paragraphs 7 to 38 and at Annex A. It was also noted that reprofiling requests had been made for two Economic Infrastructure Fund schemes, Access to York and the Better Bus Fund to 2014/15. Details of the revised 5 year capital programme were summarised at Table 2 and information on the Capital Programme financing to 2017/18 at Table 3.
Following further discussion it was
Recommended: That Council agree the adjustments in the Capital programme of a decrease of £11.659m in 2013/14 as detailed in the report and contained in Annex A. 1.
Reason: To enable the effective management and monitoring of the Council’s capital programme.