Capital Programme - Monitor Two 2013/14

Meeting: 05/11/2013 - Executive (Item 68)

Capital Programme - Monitor Two 2013/14

Decision:

[See also Part A minute]

 

Recommended:           That  Council agree the adjustments in the Capital programme of a decrease of £4.611m in 2013/14 as detailed in the report and contained in Annex A.

 

Reason:                        To enable the effective management and monitoring of the Council’s capital programme.

 

 

Minutes:

[See also Part A minute]

 

Consideration was given to a report which set out the projected capital programme outturn position for 2013/14 including any under/over spends and adjustments and requests to re-profile budgets between years.

 

The capital programme approved by Council in February, updated in the September monitor was £77.184m, financed by £42.467m of external funding and internal funding of £34.717m.  A decrease of £4.611m which was detailed in the current monitor resulting in a revised budget of £72.573m the decrease being made up of £4.403m reprofiling schemes to 2014/15 and scheme reductions of £208k, mainly arising from a reduction in the IT development plan in year spend. Details of the variances in each portfolio area were set out at Table 1 of the report with a summary of the key exceptions, implications on the capital budget and Economic Infrastructure Fund at paragraphs 8 to 42.

 

Information on the 5 year capital programme was reported at Table 2 and at Annex A and details of the capital programme financing to 2017/18 at paragraphs 45 to 47 and Table 3.

 

The Cabinet Member reported on a number of large capital projects planned for schools to provide improved accommodation and to smaller variances which affected the overall programme.

 

Recommended:           That  Council agree the adjustments in the Capital programme of a decrease of £4.611m in 2013/14 as detailed in the report and contained in Annex A. 1.

 

Reason:                        To enable the effective management and monitoring of the Council’s capital programme.

 

 


 