2007/08 City Strategy Capital Programme Outturn report

Meeting: 02/06/2008 - Executive Members for City Strategy and Advisory Panel (Item 15)

15 2007/08 City Strategy Capital Programme: Outturn Report pdf icon PDF 113 KB

This report sets out progress on schemes in the City Strategy Capital Programme during the financial year 2007/08. It is the outturn report for 2007/08 and reports on budget spend to the end of March 2008.

Additional documents:

Decision:

Consideration was given to a report which set out progress on schemes in the City Strategy Capital Programme during the 2007/08 financial year. This included the outturn report for 2007/08 and reports on budget spend to the end of March 2008.

 

The outturn for the 2007/08 Capital Programme was £8,872k, an underspend of £662k against the budget. This represents an underspend of approximately 7% against the budget, which is principally due to the Council’s £500k contribution to the Highways Agency Hopgrove Roundabout Improvement scheme not being needed in 2007/08.

 

It is proposed to carry over the following schemes from 2007/08 with funds into 2008/09. It was reported that proposals for the funding of the completion of other schemes would be made in the consolidated report to Members in July.

Proposed Carry Overs to 2008/09

Schemes

£000

A1237 Northern Bypass (Monks Cross Roundabout) - Resurfacing

60.0

Harrogate Road (part) - Resurfacing

57.0

Manor Lane (part) - Resurfacing

34.0

Hamilton Drive East/Hamilton Drive - Resurfacing

64.0

Selby Road Drainage Scheme

20.0

City Walls

18.0

Total

£253

 

 

Advice of the Advisory Panel

 

That the Advisory Panel advise the Executive Member for City Strategy to:

·        note the significant progress made in 2007/08 in implementing the City Strategy capital programme.

 

·        note the financial implications indicated in paragraphs 96 - 97.

 

·        approve the proposed carryovers amounting to £253k as outlined in paragraphs 98 - 100, subject to the approval of the Executive.

 

Decision of the Executive Member

 

RESOLVED:That the advice of the Advisory Panel be accepted and endorsed.

 

REASON:            To manage the Capital Programme effectively.

Minutes:

Consideration was given to a report which set out progress on schemes in the City Strategy Capital Programme during the 2007/08 financial year. This included the outturn report for 2007/08 and reports on budget spend to the end of March 2008.

 

The outturn for the 2007/08 Capital Programme was £8,872k, an underspend of £662k against the budget. This represented an underspend of approximately 7% against the budget, which was principally due to the Council’s £500k contribution to the Highways Agency Hopgrove Roundabout Improvement scheme not being required in 2007/08.

It was proposed to carry over the following schemes from 2007/08 with funds into 2008/09. It was reported that proposals for funding for the completion of other schemes would be made in the consolidated report to Members in July.

Proposed Carry Overs to 2008/09

Schemes

£000

A1237 Northern Bypass (Monks Cross Roundabout) - Resurfacing

60.0

Harrogate Road (part) - Resurfacing

57.0

Manor Lane (part) - Resurfacing

34.0

Hamilton Drive East/Hamilton Drive - Resurfacing

64.0

Selby Road Drainage Scheme

20.0

City Walls

18.0

Total

£253

 

Advice of the Advisory Panel

 

That the Advisory Panel advise the Executive Member for City Strategy to:

·        note the significant progress made in 2007/08 in implementing the City Strategy capital programme.

 

·        note the financial implications indicated in paragraphs 96 - 97.

 

·          approve the proposed carryovers amounting to £253k as outlined in paragraphs 98 - 100, subject to the approval of the Executive. 1.

 

Decision of the Executive Member

 

RESOLVED:       That the advice of the Advisory Panel be accepted and endorsed.

 

REASON:            To manage the Capital Programme effectively.


 

Feedback
Back to the top of the page