Reduce scope of works on Tadcaster Road Upgrade
Decision Maker: Corporate Director of Place
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: No
Decision:
Decision: Agreed to reduce scope of works on
Tadcaster Road Upgrade as outlined in the decision sheet to
minimise the project overspend.
Options Considered:
The ground conditions issues arose from an
early stage in the project and have been monitored from early in
2023. The project team initially instigated a ‘value
engineering’ exercise in conjunction with the contractor.
This is an exercise to identify where proposed works can be removed
from the scheme without detriment to the outcomes, and also where
time can be reduced by approaching the work in a different
way.
When it was realised that ‘value engineering’ on its
own would be insufficient to meet the needs of reducing costs, a
second process of more difficult decisions was undertaken. This
involved cutting back to the absolute minimum where proposed works
would be allowed to go ahead.
However it should be borne in mind that some items of work have
gone past a point of no return and have to be completed. Likewise,
finishing off processes such as carriageway surfacing, have to
address the requirements of surface regularity and therefore have
to be scheduled in.
Options Rejected:
No options were rejected in examining the
possibilities for cutting costs.
Publication date: 19/01/2024
Date of decision: 18/01/2024