Local democracy during coronavirus

During coronavirus, we've made some changes to how we're running council meetings. See our coronavirus updates for more information on meetings and decisions.

Decision details

Capital Budget 2021/22 to 2025/26

Decision Maker: Executive

Decision status: Decision Made

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

Purpose of Report: To present the capital programme, including detailed scheme proposals.

 

The Executive are asked to recommend the proposals to full Council.

Decision:

Recommended:  (i)      That Council agree the revised capital programme of £546.880m, reflecting a net overall increase of £41.037m (as set out in Table 2 at paragraph 13 of the report and in Annex A), key elements of which include:

 

a)   New schemes funded by prudential borrowing totalling £7.513m, as set out in Table 3;

b)   New schemes funded by a combination of prudential borrowing and external funds totalling £3.300m, as set out in Table 4 and summarised in Table 5;

c)   New schemes funded by a combination of prudential borrowing and other internal funds totalling £200k, as set out in Table 6;

d)   Extension of prudential borrowing funded Rolling Programme schemes totalling £10.870m, as set out in Table 5 and summarised in Table 7;

e)   Extension of externally funded Rolling Programme schemes totalling £7.00m, as set out in Table 9; and

f)     An increase in HRA-funded schemes totalling £11.954m, funded from a combination of HRA balances and Right to Buy balances, as set out in Table 10.

 

(ii)      That Council note that the total increase in council borrowing as a result of new schemes being recommended for approval is £20.483m, the details of which (schemes) are considered within this report and the financial strategy report.

 

(iii)     That Council approve the full re-stated programme totalling £546.880m, covering financial years 2021/22 to 2025/26, as set out in Table 14 at paragraph 75 of the report, and in Annex B.

 

Reason:     In accordance with the statutory requirement to set a capital budget for the forthcoming financial year.

 

 

 

 

 

Report author: Emma Audrain

Publication date: 12/02/2021

Date of decision: 11/02/2021

Decided at meeting: 11/02/2021 - Executive

Accompanying Documents:

 

Feedback
Back to the top of the page