Centre of Excellence for Disabled Children and their Families in York
Decision Maker: Decision Session - Executive Member for Children Young People and Education
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Purpose of Report: The report will provide an update of the current
cost and budget position for the Centre for Disabled
Children.
A value engineered exercise has been undertaken and further funds
are required to ensure there is an adequate contingency. This needs
to be done within this timeframe in order to meet the requirements
of external health funding.
Decision:
Resolved: (i) That an increase of £250,000 to the budget, to be funded by a virement from uncommitted resources within the Education Basic Need capital budget, be approved.
Reason: To ensure that there is adequate contingency and reduce the risk of costs exceeding the agreed budget in the construction phase.
(ii) That authority to appoint a Contractor to carry out the works be delegated to the Director of Children, Education and Communities, subject to the project being deliverable within the available budget.
Reason: In order to align the programme with that of the Lincoln Court development and enable a shared contractor to deliver both projects concurrently, thus achieving cost efficiencies.
Report author: William Shaw
Publication date: 19/06/2019
Date of decision: 18/06/2019
Decided at meeting: 18/06/2019 - Decision Session - Executive Member for Children Young People and Education
Effective from: 20/06/2019