Purpose:
Purpose of Report: This report is about the design
and consultation of the proposed upgrade of the A1237/North
Lanejunction (‘The Monks Cross
junction’). A public engagement process has recently been
completed and it is now time to conclude the detailed design and
prepare for the construction stage in early 2019. This report sets
out what has been achieved over the last few months and asks
approval to progress to the delivery stage.
The Executive Member is asked to approve and to proceed with the
detailed design and construction stages of the scheme.
Decision:
Resolved: That the Executive Member
(i) confirms that the results
of the public engagement process have been considered and
incorporated in the design where possible.
Reason: To
enable the detailed final design of the Monks Cross junction
upgrades to proceed and be completed.
(ii) notes the general arrangement design for the junction upgrade and give approval for preparations and implementation of construction (Annex 1 of the report).
Reason: To enable arrangements to be made to commence construction of the Monks Cross junction upgrade.
(iii) notes the ongoing acquisition of land and negotiation of terms and conditions by the Assistant Director Transport Highways & Environment.
Reason: To enable the acquisition of land in a timely manner in order to adhere to the York Outer Ring Road (YORR) programme.
(iv) endorses the appointment of the City of York Council’s Delivery Team for the civil engineering and associated works to undertake the Monks Cross junction upgrade.
Reason: To enable a timely appointment of a contractor which eliminates the need to go through lengthy and costly tendering processes.
Report author: Gary Frost
Publication date: 13/09/2018
Date of decision: 13/09/2018
Decided at meeting: 13/09/2018 - Decision Session - Executive Member for Transport - Expired
Effective from: 18/09/2018
Accompanying Documents:
- Report PDF 344 KB
- Annex 1 - Proposed General Arrangement for Monks Cross Junction PDF 121 KB
- Annex 2 - Layout presented for public consultation PDF 203 KB
- Annex 3 - Sample consultation package PDF 370 KB
- Annex 4 - WYCA Project Assurance Process. PDF 288 KB
- Annex 5 - Press Release for public engagement process PDF 124 KB
- Annex 6 - Frequently Asked Questions PDF 126 KB
- Annex 7 - Indicative YORR Improvement Programme PDF 516 KB
- Annex 8 - Pell Frischman report PDF 2 MB