Members considered a report which provided an update on progress with the Council’s corporate accommodation project and sought approval for a revised financial model for delivery of the project.

 

RESOLVED: (i)         That the progress of the accommodation project to date, as set out in paragraphs 4-25 of the report, be noted.

 

REASON:      In accordance with the Executive’s role in monitoring the project.

 

                        (ii)        That the revised financial model for the project, set out in paragraphs 5-21, be approved.

 

REASON:      To take account of further work carried out as part of the business case.