Decision details

Bootham - Cyclist Crossing Facility

Decision Maker: Decision Session - Executive Member for City Strategy, Executive Member for City Strategy

Decision status: Decision Made

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Purpose of report: Reports on a scheme that would provide a missing link in York's cycle network, and form part of the Haxby to Station route.

The decision was due to be made on this item at a meeting on 1 December but due to feedback from the consultation process the item will now be considered at a meeting on 5 January.

Members are asked to: Members are asked to consider the outcome of further feasibility work and consider an alternative proposal for public consultation.

Decision:

The Executive Member considered the following options:

 

·           Option One – progress the “parallel” crossing scheme proposal shown in Annex D through more detailed design and public consultation.

 

·           Option Two – develop one of the alternative scheme options in Annex C in preference to the parallel crossing.

 

·           Option Three – abandon plans to provide an improved cycle crossing facility at this location.

 

 

RESOLVED:      That the Executive Member for City Strategy agrees to-

i) Note  the officer advice that the main problems, associated with the previous full junction signalisation proposal detailed in paragraphs 5 and 6, are that the:

o        The necessary listed building and planning consents to alter the Bootham Park Hospital entrance gates are unlikely to be obtained;

o        The high estimated cost for this option brings into question whether the scheme provides good value for money and could be justified.

ii) In-principle approval for the alternative option shown in Annex D of the officer report. This involves the installation of a signal controlled ‘parallel crossing’ for both pedestrians and cyclists at a location between the existing pelican and the entrance to Bootham Park Hospital.

iii) Authorise Officers to undertake further detailed design, and public consultation, on the scheme shown in Annex D, with the outcome to be reported to a future Decision Session meeting for a decision on implementing the scheme.

 

REASON: Officers consider that these proposals will provide significant improvements for cyclists, as they address a difficult crossing point over a major road on a strategic cycle route. The proposed measures would also make a significant contribution towards the aims of the Council as a Cycling City.

Publication date: 06/01/2010

Date of decision: 05/01/2010

Decided at meeting: 05/01/2010 - Decision Session - Executive Member for City Strategy

Effective from: 08/01/2010

Accompanying Documents:

 

Feedback
Back to the top of the page