Decision details

Highways Annual Maintenance Programme 2024-25

Decision Maker: Corporate Director of Place

Decision status: Decision Made

Is Key decision?: No

Is subject to call in?: No

Decision:

The Highways Annual Maintenance Report details the range of highways assets that are managed by the Highways Asset Management service, the ways in which their needs based maintenance is assessed and how the available funding is targeted to deliver the wide range of maintenance and renewal works completed by the service in 2024-25.

The attached report, its annexes and the accompanying scheme booklets have been provided to the Corporate Director of Place for approval.

Decision:
Corporate Director, based on the information provided, approved:-
(i) The allocation of budgets for 2024-25.
(ii) The implementation of the proposed programme as outlined in the attached report and annexes.
To ensure delivery of highway maintenance services in an efficient and cost effective manner.

Options Considered:

The annual Highways maintenance programme utilises asset inspection, survey and condition data to initially assess how funding should be targeted. This is prioritised further in response to ongoing feedback from communities, businesses, elected members, partner organisations and utility providers amongst others. This is in adherence with national best practice - the Well Managed Highway Infrastructure code of practice produced by the Chartered Institute of Highways & Transportation is recognised as best practice across the industry. Highways Authorities develop programmes in adherence to its recommendations.

The programme of works has been developed in accordance with the code of practice, as such the range of projects and interventions presented in the report and it’s annexes are presented as the only option.

Options Rejected:

Not Applicable see above.

Publication date: 08/05/2024

Date of decision: 08/05/2024