Decision details
A19 Pinch Point Scheme Phase 2 - Crockey Hill
Decision Maker: Decision Session - Executive Member for Transport - Expired, Executive Member for Transport and Planning
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Purpose of Report: To
report on the result of consultation on the outline layout of
proposed changes at the A19/Crockey
Hill junction and to gain approval for the proposed delivery of the
scheme.
The Executive Member will be asked to approve the proposed delivery
of the scheme as recommended by officers.
Decision:
Resolved: That the Executive Member;
I. Noted the results of the public consultation relating to Phase 2 of the A19 Pinch Point Scheme.
II. Approved the proposed design for Phase 2 works at Crockey Hill with additional signs relating to merging in turn and using both lanes, and directed Officers to proceed to implementation.
III. Agreed that Officers would give consideration to using any contingency funding in the scheme for the proposed shared use path within the western verge and this would be reviewed as the project progressed.
Reason: The recommended design offers the best deliverable solution to increasing the southbound vehicular capacity of the A19 through Crockey Hill, whilst relieving some of the exit blocking currently experienced at the A64/A19 Fulford Interchange.
Report author: Richard Holland
Publication date: 18/08/2017
Date of decision: 17/08/2017
Decided at meeting: 17/08/2017 - Decision Session - Executive Member for Transport - Expired
Effective from: 22/08/2017