Decision details
Highways Scrutiny Ad-hoc Scrutiny Committee - Final Report
Decision Maker: Executive - for meetings from 03/06/00 to 26/04/11
Decision status: Awaiting Implementation
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Purpose of report: To inform Members of the
findings of the Highways Maintenance Procurement
Members are asked to: approve the recommendations agreed previously
by SMC
Decision:
RESOLVED:(i) That it be agreed to deal with the scrutiny recommendations as follows:
Scrutiny Committee recommendation |
Executive decision |
Part A of the Review |
|
i. That the efficiencies and other benefits gained through the PFI approach, as highlighted within the Expression of Interest (EoI) should be weighed against any budgetary inflexibility in future years, when deciding whether or not to proceed with the PFI process. |
Noted |
ii. That in the event that the PFI outcome is unsuccessful, the key issues identified should be taken into consideration when deciding upon an alternative approach. |
Agreed |
iii. That in the event that the Council’s EoI is successful, the decision to proceed to the next stage of the PFI process, i.e. submitting an Outline Business Case (OBC), be weighed against the resulting greater annual budget commitment required from the Council if the highways repair and maintenance works are to be carried out. |
Noted |
iv. That it should be noted that as there are too many unknown quantities at this stage in the process, the total expenditure over the lifespan of the PFI cannot be properly identified. |
Noted |
v. That in the event that the EoI is successful, careful consideration should be given when deciding whether to proceed to each of the following stages of the process, thereby ensuring a full understanding of the cost implications. |
Noted |
Part B of the Review |
|
i. That there has been an impact on the repayments to the Venture Fund caused by the delays in implementing the actions agreed as part of the Best Value Review |
Noted |
ii. The delays in implementing the actions agreed as part of the Best Value Review were necessary |
Agreed |
iii. The total savings made in Highways Maintenance since the Best Value Review are significantly higher than those identified therefore there has been no financial loss to the council caused by the delays in the procurement process |
Agreed |
REASON: To enable the Executive to introduce appropriate changes to working practices and/or Council policy and procedures.
Publication date: 22/04/2008
Date of decision: 22/04/2008
Decided at meeting: 22/04/2008 - Executive - for meetings from 03/06/00 to 26/04/11
Effective from: 25/04/2008
Accompanying Documents:
- Committee Report for Highways Scrutiny Final Report PDF 38 KB
- Final Report for Part A of the Highways Ad-hoc Scrutiny Review PDF 73 KB
- Part A - Annex A PDF 15 KB
- Part A - Annex B PDF 16 KB
- Part A - Annex C PDF 95 KB
- Part B Final Report PDF 53 KB
- Part B - Annex A PDF 35 KB
- Part B - Annex B PDF 75 KB
- Part B - Annex C PDF 44 KB
- Part B - Annex D PDF 34 KB
- Part B - Annex E PDF 37 KB