Decision details

James House Temporary Homeless Accommodation - Approval for Budget Revisions and Authorisation to Appoint the Successful Contractor

Decision Maker: Executive

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

Recommended: That Council approve the revised budget of £12.4m for the James House project, financed from £2.451m Homes England grant and £9.949m from the Housing Revenue Account (investment reserve, capital receipts and commuted sums), thereby ensuring no increase in cost to the council).

 

Reason:              To enable the construction contract for the new homeless accommodation at James House to be awarded, £2.451m Homes England grant funding to be claimed, and a start on site achieved by 29 March 2018.

 

 

 

 

 

Publication date: 15/03/2018

Date of decision: 15/03/2018

Decided at meeting: 15/03/2018 - Executive

 