Decision details

Capital Programme Budget 2013/14 to 2017/18

Decision Maker: Executive

Decision status: Decision Made

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Purpose of Report: To present the 5 year capital programme budget 13/14 to 17/18 including new capital schemes and appropriate funding arrangements, following this years Capital Resource Allocation Model (CRAM) process.
Members are to recommend to Full Council the approval of the 5 year Capital Programme budget 13/14 to 17/18, the new schemes and the associated funding.

Decision:

RECOMMENDED:    That Council:

 

i)    Agree to the revised capital programme of £176.709m, that reflects a net overall increase of £48.381m as set out in paragraph 30 table 10 and in Annex A ‘budget amendments’ column). Key elements of this include:

 

o    Extension of prudential borrowing funded Rolling Programme schemes totalling £3.365m including the IT development fund as set out in paragraph 10 table 2 and summarised in paragraph 27 table 9;

o    Creation of 2 new prudential borrowing funded Rolling Programme schemes totalling £1.500m as set out in paragraph 14 table 3 and summarised in paragraph 27 table 9

o    New  schemes totalling £3.585m including an increase in prudential borrowing of £3.185m as set out in paragraph 16 table 4 and summarised in paragraph 27 table 9;

o    New externally funded schemes totalling £25.974m as set out in paragraph 18 table 5 and summarised in paragraph 26 table 9

o    An increase in HRA funded schemes totalling £13.957m funded from HRA balances of £13.957m as set out in paragraph 19 table 6 and summarised in paragraph 27 table 9.

 

ii)   Approve the full restated programme as summarised in Annex A totalling £176.709m cover financial years 2013/14 to 2017/18 as set out in paragraph 30 table 10.

 

REASON:                        To set a balanced capital programme as required by the Local Government Act 2003.

 

Report author: Louise Branford-White

Publication date: 13/02/2013

Date of decision: 12/02/2013

Decided at meeting: 12/02/2013 - Executive

Effective from: 15/02/2013