Decision details

A19/A1237 Roundabout Improvements - Consultation Results and Detailed Design

Decision Maker: Decision Session - Executive Member for City Strategy

Decision status: Decision Made

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Purpose of report: To inform the Executive Member of the results of the public consultation on the outline design for the A19/A1237 Scheme. To obtain approval for the detailed design for the improvements to allow the scheme to progress through to construction.

Members are asked to: Approve the layout for the A19/A1237 roundabout improvements to be taken forward to construction.

Decision:

RESOLVED:            That the Executive Member agrees to:

i) Note the comments raised by the public, Councillors and interested organisations.

ii) Note the Officer’s response to the comments and the proposed amendments to the design.

iii) Approve the further development of the scheme in line with the amended layout subject to the removal of the rumble strips on Shipton Road, as part of the necessary resurfacing works, to enable the improvements to be tendered and constructed in the summer/autumn of 2010.

iv) Approve the inclusion of a total allocation of £1.5m in the City Strategy Capital Programme to construct the proposed scheme.

v) Authorise the removal of the minimum amount of vegetation from the A1237 West landscaped bund in February, to allow the main works to proceed later in the year to minimise the impact on nesting birds.

REASON:                  To reduce journey times for travellers in the A19/A1237 area whilst maintaining safe crossing points for pedestrians and cyclists.

 

Publication date: 03/02/2010

Date of decision: 02/02/2010

Decided at meeting: 02/02/2010 - Decision Session - Executive Member for City Strategy

Effective from: 05/02/2010