Access York Park & Ride Development - Update Report Following Programme Entry
- 15/03/2010 - Published in plan, 15 March 2010 to 28 July 2010
- 13/04/2010 - Agenda item, Executive - for meetings from 03/06/00 to 26/04/11 Access York Park & Ride Development - Update Report Following Programme Entry 13/04/2010
- 13/04/2010 - Published decision: Access York Park & Ride Development - Update Report Following Programme Entry
- 15/04/2010 - Call-in period expired: Access York Park & Ride Development - Update Report Following Programme Entry
- 19/04/2010 - Agenda item scheduled, Corporate Services, Climate Change and Scrutiny Management Committee (Calling In)
- 11/05/2010 - Action: 2. Complete any required actions for the procurement of Halcrow as Lead Design Consultant Paul Thackray ; status: overdue
- 11/05/2010 - Action: 1. Progress the project in accordance with the agreed contributions / funding sources Paul Thackray ; status: overdue