Access York Park & Ride Development - Update Report Following Programme Entry
Decision Maker: Executive - for meetings from 03/06/00 to 26/04/11
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Purpose of report: The
CYC element of the funding for the Access York Phase 1 scheme would
be approved. This would allow the scheme to progress and with
officers involved in works with the lead design consultant,
Halcrow. Further reports will be brought to Members regarding
detailed design options for works affected the public highway, as
well as reports on the procurement of the construction contractor.
Detailed design reports should be available in September 2010. The
key contractor procurement reports will be in Spring 2011.
Members are asked to: Approve the CYC financial contribution to the
scheme and approve the appointment of Halcrow as lead design
consultant.
Decision:
RESOLVED: (i) That the City of York Council contributions for the Access York Phase 1 project, as set out in the anticipated spend / funding profile in paragraph 11 of the report and the potential funding sources in paragraph 14, be approved.
(ii) That the procurement of Halcrow as the Lead Design Consultant be approved.
REASON: To enable the Access York Phase 1 project to proceed as planned by providing the required funding and approving the procurement of a Lead Design Consultant.
Report author: Paul Thackray
Publication date: 13/04/2010
Date of decision: 13/04/2010
Decided at meeting: 13/04/2010 - Executive - for meetings from 03/06/00 to 26/04/11
Effective from: 16/04/2010