Issue - meetings

Economy & Place Transport Capital Programme – 2018/19 Monitor 2 Report

Meeting: 20/12/2018 - Decision Session - Executive Member for Transport (Item 60)

60 Directorate of Economy & Place Transport Capital Programme - 2018/19 Monitor 2 Report pdf icon PDF 193 KB

This report sets out progress to date on schemes in the 2018/19 Economy & Place Transport Capital Programme, and proposes adjustments to scheme allocations to align with the latest cost estimates and delivery projections.

Additional documents:

Decision:

Resolved:

 

i)             That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved.

 

ii)            That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted.

 

iii)          That the proposed improvements to cycle routes on the approaches to the new Scarborough Bridge footbridge be approved (with the St. Mary’s ramp allocation increased to £45k) to allow the schemes to be implemented as part of the footbridge replacement scheme.

 

Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.

 

Minutes:

The Executive member considered a report that set out progress to date on schemes in the 2018/19 Economy & Place Transport Capital Programme, and proposed adjustments to scheme allocations to align with the latest cost estimates and delivery projections.

 

Officers provided an update on major schemes and transport schemes for 2018-19. With regard to the Scarborough Bridge Route Improvements, they advised that the cost for the replacement of the steps between St Mary’s to St Mary’s Lane with a ramp should be £45,000 but this this increase could be accommodated in the overall underspend for the bridge.

 

The Executive Member noted that a separate report on Scarborough Bridge would be prepared for his consideration at a future meeting.

 

Resolved:

 

i)             That the amendments to the 2018/19 Economy & Place Transport Capital Programme be approved.

 

ii)            That the decrease to the 2018/19 Economy & Place Transport Capital Programme, subject to approval by the Executive, be noted.

 

iii)          That the proposed improvements to cycle routes on the approaches to the new Scarborough Bridge footbridge be approved (with the St. Mary’s ramp allocation increased to £45k) to allow the schemes to be implemented as part of the footbridge replacement scheme.

 

Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme.

 

 


 

Feedback
Back to the top of the page