Decisions

Decisions published

28/06/2024 - York Station Gateway – Design Changes, Bus Stops and Materiality ref: 7189    Decision Made

Decision Maker: Chief Operating Officer

Decision published: 26/07/2024

Effective from: 28/06/2024

Decision:

Following an extensive public consultation, the York Station Gateway received planning (19/00535/FULM) and listed building consent on 4th February 2021. Consequently, following the successful completion of a package (P1) of utility diversionary works, the highways works packages (P2 and P4) were tendered and awarded in summer 2023. Works on the P2 scheme began on site in October 2023 with a view to an instruction to commence P4 works in autumn 2024 once land acquisition had taken place and other funding conditions had been met.

During a project delivery update presentation to the York Access Forum (YAF) on 22nd November 2024, issues were raised by the YAF over the suitability of the scheme compliance with relevant standards in the design of the scheme, regarding cycleways and the choice of materials. The issues highlighted were particularly related to comments from residents with reduced mobility, hearing difficulties and the blind and partially sighted. The issues raised comprised:

1. The geometry of the junction at the exit to the loop road
2. The signalised crossing at the York RI
3. The design, orientation and quantity of pedestrian crossings over proposed cycleways
4. The quantity of bus stops, and location and orientation of bus shelters
5. The choice and design of traffic signals
6. The colour and type of materials in cycleways and the public realms
7. The quantity, location and type of bollards across the proposed scheme

Subsequently, further issues were raised by the York Bus Forum (YBF) on the proposal to maintain the quantity of bus stands at the present four in either direction in the proposed scheme.

To address the issues raised, the project team organised a series of consultation workshops with the Council’s Accessibility Officer, YAF and YBF throughout January to March 2024 to agree permissible changes to the design that could be made within the available time given that works were already taking place on site. These meetings were attended by accessibility and bus stakeholders, together with Council highways officers and scheme designers. By April 2024, design changes had been agreed and the project designers began work on formalising the changes in the design and in the preparation of updated construction information.

The output from this engagement and workshops delivers an updated scheme that proposes improvements to the layout of the Highway and Public Ream, incorporating recognised best practice and compliance with all relevant national guidelines.
The proposed updates to the permitted layout are itemised in Appendix 1 (to be read in conjunction with updated general arrangement drawing in Appendix 2) to this decision paper but are summarized as follows:

1. The geometry of the junction at the exit to the loop road
The YAF identified that the exit to the loop would cause issues to blind and partially sighted residents owing to a road crossing followed by a further cycleway crossing. The configuration was thought to be excessive as it would force pedestrians to cross two rather than a single trafficked space. The junction layout was amended to provide a single carriageway lane at the junction and the provision of an uncontrolled crossing and continuous footway. The impact of this change is the potential reduction in junction capacity and increased queuing on the RI loop road at the junction, especially if Queen Street is queueing from Blossom Street.

2. The signalised crossing at the York RI
The existing arrangement proposed a Y-shaped junction crossing in front of the York RI that was envisaged to facilitate movements of cycles and pedestrians. This arrangement proved contentious with both YAF and with the Council’s own signal engineers. This cycle crossing position and alignment has been updated to remove Y-shape crossing and ensure that it is in accordance with current regulations. The revised arrangement partially restricts cycle movements travelling south across the crossing and turning right onto Queen Street and travelling towards Blossom Street when compared to the previous arrangement. The new arrangement may also adversely impact queuing on Blossom Street.

3. The design, orientation and quantity of pedestrian crossings over proposed cycleways
The YAF identified several uncontrolled pedestrian crossings that owing to their non-perpendicular orientation could cause difficulties for all pedestrian users. It was also suggested that there were an excessive number of crossings causing confusion and slowing down the movement of pedestrians. The updated design rationalizes the quantity of crossings and where possible has sought to square up crossings in several locations. To increase the visibility of crossings a bollard is proposed on opposing corners of the entrance to the crossing.

4. The quantity of bus stops, and location and orientation of bus shelters
In the original design, bus shelters were located adjacent to the curb, open to the rear. The YAF explained that this orientation would cause access issues for most users, whilst the YBF suggested that it would also be more difficult for bus drivers to negotiate. In the updated design, bus shelter locations and orientation have been relocated to the back of the footways, open to the front, and shown with an updated flag and feeder pillar position.
The permitted scheme approved by the Local Planning Authority showed a relocated bus interchange moved from outside the York Station portico to occupy a redeveloped area of the Inner Ring Road in front of the arches in the City Walls once occupied by the Queen Street Bridge. The general arrangement drawing submitted showed an indicative 5 number bus stops on either side of the Inner Ring Road (see Figure 1).


Figure 1 – Permitted Scheme (attached as document)

It is stressed that this arrangement submitted to the LPA by the designers was indicative only, with the final arrangement for the bus laybys to be determined and agreed by The Council’s Public Transport Team in due course in consultation with bus partners.

The length of the proposed bus layby measures 85m (excluding layby tapers) on either side of the road. In the existing arrangement, although on the station side of the road there is a unique 3 + 1 bus stop arrangement, on the City Walls side, the existing bus layby arrangement measures 82m (excluding layby tapers). The Public Transport Team has determined that as a bus stop must be a minimum of 18m to comfortably dock at a bus stop, that 4 bus stops of 21m in length is the optimum for the proposed provided length (see Figure 2 attached as document).



Figure 2 – Bus Stop Lengths

Further guidance on the design of bus stops can be found at https://content.tfl.gov.uk/bus-stop-design-guidance.pdf which recommends considerably longer lengths than the 18m minimum length bus stands typically proposed by City of York Council. The TFL guidance is accepted as the standard and recommended to all authorities on the DfT’s Bus Centre of Excellence website (https://www.buscentreofexcellence.org.uk/). The proposed scheme is broadly comparable in length to the existing scheme and to increase the number of stands would cause significant bus congestion and raise safety and accessibility concerns.

The loop road package at the Station Gateway scheme delivers a further 3 bus stops which will contribute to future enhanced capacity. The Public Transport team is currently working with bus operators on which services should be transferred to the Loop Road stops, to further optimise future service delivery.

In planning terms, a decision to formalize an 8-bus stop configuration is a non-material change. A decision is required as to formalize the bus stop configuration outside York Station to 4 stops on either side of the Inner Ring Road with a further 3 stops on the Loop Road. However, we will be enlarging the 4 stops on either side, to increase the waiting passenger capacity by 20%.
5. The choice of traffic signals
The YAF requested the inclusion of pedestrian crossing countdown timer aspects to be installed on traffic signals. However, subsequent conversations with the Council’s traffic signals team and scheme designers ruled out this option as the proposed puffin crossing were regarded as the safest and most appropriate and are standard across the city. Whilst puffin/nearside traffic management is the Council’s Traffic signals team’s preferred option, which align with signal crossings across the city, Council is prepared to trial the use of the countdown timer signal on York Station Gateway. We believe this may reflect a longer-term preference, aligning with the new local transport strategy, which was approved by the council executive in July 2024.
6. The colour and type of materials in cycleways and the public realms
Granite setts is the proposed material for cycleways and pedestrian crossing in the consented scheme. However, YAF members challenged this choice believing it is not appropriate from an accessibility standpoint owing to the lack of colour contrast between adjacent materials. Although, the technical specification for the proposed materials conformed to guidance values for contrasting Light Reflectance Values (LRV), the YAF proposed alternative materials. After much debate, the project team agreed that a pigmented (i.e., coloured) tarmac would be the best option. The recommended colour has now been agreed as green with YAF, which complies with LTN 1/20 guidance. Artist impressions of this colour, as well as terracotta (which was also considered) and the proposed granite, are shown in Appendix 2 of this paper. This decision was further supported through more recent feedback from charity Wheels for Wellbeing and RNIB.
7. The quantity, location, and type of bollards across the proposed scheme
In the consented scheme, there are two bollard types proposed: those to secure the front of the station from Hostile Vehicle (HVM) attacks, and those to prevent unlawful parking. Owing to obstructions caused by bollards, YAF proposed that where possible, any unnecessary vehicle parking deterrent bollards be removed from the scheme. In reviewing the scheme, the project team has sought to rationalize the use of parking bollards. The YAF accepted that the number of HVM bollards could not be reduced, removed, or relocated.

Though not an accessibility issue, this paper also seeks a further decision on the manufacturer choice of bus shelter to be installed in the scheme.
In York, many bus shelters are currently supplied and maintained by a company known as JCDecaux as an advertising concession, including those shelters located to the front of York Station. It is the project team’s understanding that in considering re-awarding the current contract with JCDecaux, The Council was unable to justify making a direct contract award is now carrying out a competitive tender. This process will not be completed within the Station Gateway project timescales. Consequently, this will result in the removal of the existing four shelters at the station on completion of the existing contract if it is not renewed.
The York Station Gateway scheme requires eight number new bus shelters to be installed in autumn 2024. Following prior work carried out by the Public Transport Team, a bespoke high quality shelter design had been agreed with a company known as Etesian Green (see Appendix 6). This has been proposed for the Station Gateway scheme as an alternative to the JCDecaux shelters. It is the project team’s understanding that these shelters would cost £18,000 each, and a total of £144,000 for the eight shelters. The project team is happy to accept this proposed shelter and the project consultants, Arup, and delivery contractor, Sisk, have confirmed that this shelter is suitable for installation at the site.

There is a 12-week lead in period for the delivery of the Etesian Green bus shelter and the contractor has factored this into its programme. The contractor can procure the shelters on The Council’s behalf although a management fee will be applied.

A decision is required as to whether to proceed with an instruction to the contractor, Sisk, to procure and supply the Etesian Green bus shelters for the York Station Gateway scheme at a sum of £144k + fees (circa £20k). The cost of the shelters will be covered from the schemes existing funding resources.

This decision paper seeks five decisions as follows:
1. Accept the proposed geometrical and junction design changes to the permitted scheme so that an instruction can be provided to the Package 2 delivery contractor to construct the updated design.

2. Accept the proposal to maintain the current number of bus stands in the proposed scheme as 4 stops in either direction plus three new stands on the proposed loop road but increase waiting passenger capacity of bus shelters by 20%.

3. Accept the proposed Etesian Green shelter to be installed across the site to allow Package 2 delivery contractor to place an order for this product.

4. Accept the proposed changes to the materiality of the permitted scheme so that an instruction can be provided to the Package 2 delivery contractor to order and construct the updated layout using these materials, including the decision to substitute granite sets in the cycle way to a green-coloured tarmac.

5. Accept the use of countdown timer traffic signals as a pilot scheme, on York Station Gateway.

Wards affected: Micklegate Ward;

Lead officer: James Gilchrist


12/07/2024 - Addition disabled parking bay to the Traffic Regulation Order ref: 7161    Decision Made

Decision Maker: Chief Operating Officer

Decision published: 12/07/2024

Effective from: 12/07/2024

Decision:

The resident who applied for a disabled parking bay on Long Close Lane has reported there is consistent abuse of the bay by non-blue badge holders and this is preventing the resident from using the bay.

Any requests for Blue Badge parking bays in residential areas are initially introduced as advisory bays, to provide the facility on street in a more efficient way. The bay is not enforceable if non blue badge holders park in them, so the bay is then not useable by Blue Badge Holder.

It is proposed to undertake the statutory consultation for the advertisement for the addition of the Blue badge Parking Bay into the Traffic Regulation Order, so enforcement of non-blue badge bays can occur.

Decision:
Advertise a traffic regulation order change to include the current advisory disabled parking bay on the Traffic Regulation Order, if approved non blue badge holders parking in the bay could be enforced and help to resolve the abuse currently taking place.

Wards affected: Guildhall Ward;

Lead officer: James Gilchrist


12/07/2024 - To remove disabled parking bays from the Traffic Regulation Order ref: 7160    Decision Made

Decision Maker: Chief Operating Officer

Decision published: 12/07/2024

Effective from: 12/07/2024

Decision:

The families of two deceased residents contacted us to advise the disabled parking bays are no longer required, and requested we remove them.

The bays are located on Alma Terrace and Sutherland Street, the removal of the bays will require an amendment to the Traffic Regulation Order (TRO), to remove the bays from the Order.

Approval is requested to undertake the statutory consultation to advertise an amendment to the TRO for the removal of the bays.

Decision:
To remove disabled parking bays from the Traffic Regulation Order

Wards affected: Fishergate Ward; Micklegate Ward;

Lead officer: James Gilchrist


12/07/2024 - Advertise an Amendment to the Traffic Regulation Order to introduce ‘No Waiting at any time’ restrictions in Mansfield Street ref: 7159    Decision Made

Decision Maker: Chief Operating Officer

Decision published: 12/07/2024

Effective from: 12/07/2024

Decision:

Two recent developments have created an issue regarding unrestricted parking on Mansfield Street. There is a section 106 agreement in place for the development, as there were concerns within the planning that the development would create a parking issue on the street.

Wards affected: Guildhall Ward;

Lead officer: James Gilchrist


05/07/2024 - Amendments to the Waste Policy regarding the introduction of a garden waste subscription service. ref: 7158    Decision Made

Decision Maker: Chief Operating Officer

Decision published: 09/07/2024

Effective from: 05/07/2024

Decision:

At Executive meeting in January 2024 Executive approved a Waste Policy and at
full Council in February 2024, as part of the budget, Executive approved the introduction of a garden waste subscription scheme for city.

The garden waste service in York is currently delivered to 66,000 households. A garden waste subscription scheme has been developed and as part of the development of the scheme, the Council has established terms and conditions to outline how the scheme will operate. As a result of this change, it is necessary to update the Waste Policy to reflect the introduction of a garden waste subscription scheme across the city.

The garden waste subscription scheme is being launched in July 2024 with the operational ‘Go Live’ set for Monday 5th August 2024 onwards. The Council will write to the 66,000 households who currently receive the garden waste service and residents will have the opportunity to subscribe to the garden waste subscription scheme if they so wish and pay a subscription fee. There are other options available to residents as they can (i) share a garden subscription with a neighbour (ii) purchase a discounted home composter so they can compost at home or (iii) take garden waste to the household waste recycling centres (HWRC’s), free of charge.

To reflect the introduction of the garden waste subscription service, Waste Services need to seek authorisation for the terms and conditions of the scheme and to amend the Waste Policy to reflect the updated section(s) of the Policy. Only the section(s) that refers to garden waste and bins for garden waste will need to be updated.

It is proposed that these changes are made with effect from Monday 8th July 2024.

Wards affected: (All Wards);

Lead officer: James Gilchrist


08/07/2024 - To award the Healthwatch York contract 2024-2028 to York CVS ref: 7157    Decision Made

Decision Maker: Director of Customer & Communities

Decision published: 09/07/2024

Effective from: 08/07/2024

Decision:

To approve the award of the Healthwatch York service to York CVS for the period 1st August 2024 – 31st July 2028

For the provision of services as outlined in the supporting report.

Wards affected: (All Wards);

Lead officer: Pauline Stuchfield


03/07/2024 - This decision is to limit the value of resettlement support paid through York financial Assistance Scheme (YFAS) to £500 per family (This includes single people), to cap the monthly spend through YFAS to £20,000 per month during the rest of the 2024/ ref: 7156    Decision Made

Decision Maker: Director of Customer & Communities

Decision published: 08/07/2024

Effective from: 03/07/2024

Decision:

The Director of Housing and Communities approves the YFAS changes as set out in this decision notice and in the supporting report.

This is an officer decision made in consultation with the relevant Executive Members and will be noted at the next available Executive Member Decision Session.

Wards affected: (All Wards);

Lead officer: Pauline Stuchfield


03/07/2024 - Ward Schemes (Batch 5) – Approval of Ward Revenue Budget Spend 2024 ref: 7155    Decision Made

Decision Maker: Director of Customer & Communities

Decision published: 05/07/2024

Effective from: 03/07/2024

Decision:

Ward Budget pending decisions are delegated to the Director of Customer and Communities on the recommendation of ward members as per the attached report .
Recently recommended schemes to be approved are attached at the Annex to the report.

Wards affected: Bishopthorpe Ward; Clifton Ward; Fishergate Ward; Fulford and Heslington Ward; Haxby and Wigginton Ward; Rural West York Ward;

Lead officer: Pauline Stuchfield


27/06/2024 - City Wall closure for Piling Works ref: 7154    Decision Made

Decision Maker: Corporate Director of Place

Decision published: 28/06/2024

Effective from: 27/06/2024

Decision:

York Station Gateway Project – Package 2.
Permanent closure of the City Walls between Station Rise and Micklegate Bar for a further 4-week period until high-risk activity - piling works are complete and Health and Safety measures have been put in place.
The extension to the closure is required owing to unexpected ground conditions which required further design to the piling, and equipment breakdown delaying the piling works.
The 4-week closure allows safety measures to be installed, enabling the walls to be opened safely from Friday 26th July 2024, or earlier subject to a further risk assessment.
Decision - Implement Option 3. Whilst further closure is unfortunate public safety is a priority and I note work to find a solution to allow access is planned for the summer holidays.

Wards affected: Micklegate Ward;

Lead officer: James Gilchrist


17/06/2024 - To make an order in response to the 202308 Dunnington Priest Lane DMMO application. ref: 7153    Decision Made

Decision Maker: Corporate Director of Place

Decision published: 28/06/2024

Effective from: 17/06/2024

Decision:

There is sufficient evidence to meet the statutory test under s53 (3) of the Wildlife and Countryside Act 1981 to make an order to record a public restricted byway over Priest Lane as shown on the map (see separate attached document).

Decision: Agreed to make an order to record a public restricted byway along Priest Lane but take a neutral stance towards the confirmation of the order in the event it is referred to the Secretary of State.

Wards affected: Osbaldwick and Derwent Ward;

Lead officer: James Gilchrist


 

Feedback
Back to the top of the page