To commission improvements to Acomb Front Street and allocate £395k from the York UKSPF investment plan to fund the work
05/12/2022 - To commission improvements to Acomb Front Street and allocate £395k from the York UKSPF investment plan to fund the work
Approval from Government for the York UKSPF
Investment Plan is expected in November or December 2022. In order
to undertake work beginning in January, orders must be placed for
the necessary supplies by the end of November. This means that a
decision must be taken to pre-allocate UKSPF funds to the project
prior to formal approval from Government. In the unlikely event
that the Government funding does not materialise, the work will be
funded from the council’s capital highway maintenance budget.
This can be managed through anticipated slippage of the programme
in 2022/23 and the 2 year impact will be incorporated into the
2023/24 programme that is agreed after the final budget is approved
in February 2023.
Decision made : To commission highways improvements in Acomb Front
Street and allocate £395k from the York UKSPF Investment Plan
(intervention E1) to the work, with the anticipated split between
years to be £250k in 2022/23 and £145k in
2023/24.