Enter Deed of Variation for Lowfield Green with Wates Construction

24/11/2022 - Enter Deed of Variation for Lowfield Green with Wates Construction

The decision has been taken to enter the Deed of Variation with Wates Construction to change the completion dates and contract sum of the original Lowfield Green contract in light of the delays experienced on the site since the Covid 19 pandemic. The decision has been taken following comprehensive financial and legal advice. Entering the Deed of Variation effectively extends the terms of the existing contract to the completion date of the 7th March and fixes the contract sum to prevent further inflationary increases.


 