Decision details
Mayoral Renewables Fund (MRF) Grant Agreement with Great British Energy (GBE) and York and North Yorkshire Combined Authority – GBE to pay £42,760 to City of York Council for solar PV installation at Moor Lane Youth Centre. CYC to fund enabling new r
Decision Maker: Director of Housing and Communities
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: No
Decision:
Mayoral Renewables Fund (MRF) Grant Agreement
with Great British Energy (GBE) and York and North Yorkshire
Combined Authority – GBE to pay £42,760 to City of York
Council for solar PV installation at Moor Lane Youth Centre. CYC to
fund enabling new roof works from existing capital sinking
fund.
The Mayoral Renewables Fund (MRF) is a grant scheme for Mayoral
Strategic Authorities (MSAs) to develop renewable energy projects
in their localities. The scheme forms part of Great British
Energy’s (GBE) early delivery phase in the 2025 to 2026
financial year.
York and North Yorkshire Mayoral Combined Authority (YNYCA) has
been awarded £700,000 by GBE, of which £216,000 has
already been allocated to York to fund Solar PV installation at
three sites: Yearsley Swimming Pool, Joseph Rowntree School and
Acomb Explore Library.
A further grant has been awarded for £42,760 for solar PV at
Moor Lane Youth Centre. The enabling works required for the solar
PV is a new roof,– the roof works were due in any case
necessary due to their age and condition. These works are estimated
at C.£200k and funding from the existing community centre
capital sinking fund is possible.
The predicated project outcomes will be :(subject to final
design)
• £2,768 saving pa+vat
• 13,840kWh Est Annual Gen
• 2.86 tCO2e Carbon Em save/pa
• 71.62 tCO2e Carbon Em save over lifetime of project
Policy Context
This decision contributes to several key council policies:
• Council Plan: Climate Change Core Commitment Objective 5:
Increase sources of renewable energy.
• Climate Change Strategy Objectives 7.1 and 7.2: Increase
renewable generation capacity and improve energy flexibility and
storage.
• Climate Change Action Plan: Actions to explore opportunities
for renewable generation and support increase of solar capacity
across York including homes, schools, and community energy
schemes.
• Aligns with York’s Local Area Energy Plan
(LAEP).
Options Considered:
Option 1: Approve the GBE Grant Agreement with
CYC and allocate the capital budget of £200k from the sinking
fund to allow the enabling works
Option 2: Reject the GBE Grant Agreement with CYC
Options Rejected:
Option 2: As this funding will allow CYC to
complete a renewable project which would otherwise likely not go
ahead, and there is sufficient capital funding from the community
centre sinking fund to carry out the enabling works, that Option 2
should be rejected.
Publication date: 06/11/2025
Date of decision: 06/11/2025